GB/T 19620-2004 Labor quota for urban rail transit electric traction power supply engineering
Some standard content:
ICS 03. 100.30
National Standard of the People's Republic of China
GB/T19620—2004
Labor force quota for locomotive power supply engineeringin city transit system
Promulgated on 2004-12-28
General Administration of Quality Supervision, Inspection and Quarantine of the People's Republic of China Administration of Standardization of the People's Republic of China
Implementation on 2005-07-01
GB/T19620—2004
Labor force quota for locomotive power supply engineeringin city transit system 2
2.1 Overhead network
2.2 Traction substation
2.3 Power engineering
Appendix A (Normative Appendix) Relevant provisions for use References
...............
GB/T19620—2004
The labor quota and quota series of urban rail transit engineering consists of standards such as "Labor quota and quota of urban rail transit light rail engineering", "Labor quota and quota of urban rail transit underground railway engineering", "Labor quota and quota of urban rail transit communication signal engineering", "Labor quota and quota of urban rail transit traction and power supply engineering", "Labor quota and quota of rail transit engineering machinery repair", and "Labor quota and quota of rail transit engineering industrial manufacturing". GB/T19620-2004 "Labor quota and quota of urban rail transit traction and power supply engineering" is one of the labor quota and quota series of urban rail transit engineering.
Appendix A of this standard is a normative appendix.
This standard is proposed by the National Technical Committee for Labor Quota and Staffing Standardization. This standard is under the jurisdiction of the Ministry of Labor and Social Security. The main drafting unit of this standard: China Railway Engineering Corporation. The main drafters of this standard are: Pang Dejing, Li Bingxin, Li Hua, Liu Jiansheng, Zhang Shenglin, Yu Zhongliang, Cai Wenhai. The main editors of this standard are: Li Changjin, Ma Li, Wu Zelin, Wang Shucheng, Xia Heping, Zhang Junhui, Jin Liancheng, Yan Zhongwei, Du Wenlong, Xu Jiaqiang, Wang Qingzhong, Liu Yinghua, Liu Junjie, Zhang Xiaoping, Zeng Linghui, Hua Fujun, Huang Hu, Li Yun. This standard is interpreted by the China Railway Engineering Labor Quota and Staffing Standardization Technical Committee. I
GB/T19620—2004
The formulation of this standard provides the main basis for guiding and regulating the construction and production of urban rail transit projects, strengthening labor management, and enterprises to rationally allocate labor and formulate work plans; at the same time, it provides standards for economic quotas such as budget quotas and machine shift quotas of urban rail transit projects and financial labor cost management.
This standard, in accordance with the principle of "advanced, reasonable, scientific and standardized" and the construction process of urban rail transit traction power supply projects, briefly describes the work content and operation methods of each process (post); stipulates the labor quota, quota, machinery (equipment) conditions, skill requirements of practitioners and adjustment coefficient standards for each process (post).
1 Scope
Labor quota of urban rail transit electric traction power supply projects
GB/T19620—2004
This standard stipulates the labor quota, quota, skill level, personnel allocation and work content of urban rail transit electric traction power supply projects. This standard applies to the labor management of urban rail transit electric traction power supply projects. 2 Labor quota for urban rail transit electric traction power supply project 2.1 Contact network
2.1.1 Construction measurement
2.1.1.1 Work content:
Station yard longitudinal measurement: determine the position of the tower, write numbers, check drawings, and record; a)
Station yard pile measurement: find piles, pull rulers, measure center elevations, set piles, record, and calculate; c)
Section longitudinal measurement: measure length, span, check drawings, write numbers, and determine the position of the pole pit: Longitudinal measurement in the tunnel: measure length, span, check drawings, and write numbers; d)
Measurement of suspension points in the tunnel: measure suspension points, ground wire suspension points, write numbers, check drawings, record, lighting, and push ladders; flange measurement: check drawings, measure, and record. Staffing: 1 technician, 2 senior technicians, 2 intermediate technicians, and 3 junior technicians, a total of 8 people. The man-day quota is shown in Table 1.
Table 1 Square
Construction measurement
Station yard (less than 8 tracks)
Intersection pile measurement
Project/station
Excavation of pole pit, foundation pit
Ordinary soil
Sub-hard rock
Vertical measurement
Man-day/(line·km)
Inside the tunnel
Suspension point measurement
Flange
Man-day/place
Work content: excavation, earth pouring, cleaning, wood preparation, transportation, board protection, box racking, quicksand pit, landslide pit wall protection. Staffing: 1 senior technician, 1 intermediate technician, 3 junior technicians, a total of 5 people. The man-day quota is shown in Table 2.
General pole pit, wire pit anchor column, conversion column pit 1.28
Note: For relevant regulations, see Appendix AA.6, A.7, A.10. Transportation of foundation materials
Excavation of pole pit, foundation pit
Soft cross pole pit
2.1.3.1 Work content: loading and unloading, lifting and transportation of sand, stone, cement and other materials, and monorail transportation. II-5
Unit is man-day per
GB/T19620—2004
Staffing: 2 intermediate technicians, 14 junior technicians, a total of 16 people. See Table 3 for man-day quota.
Do not cross the railway
Cross the railway
Loading and unloading 50m
Every additional 50m
1 to 5 tracks
Every additional track
Install the foundation model plate
2. 1.4. 1
Basic material transportation
Work content: transport materials, install model plates, install frames and foundation bolts. II-9
Staffing: 1 senior technician, 1 intermediate technician, 2 junior technicians, a total of 4 people. The work day quota is shown in Table 4.
Table 4 Installation of foundation model plate
Foundation pouring and maintenance
Unit is man-days each
Unit is man-days each
Work content: cleaning the site, setting up a mixing platform, transporting materials within 50m, washing stones, mixing, pouring, tamping, connecting power supply, water source, and transfer. Staffing: 2 senior technicians, 5 intermediate technicians, 18 junior technicians, a total of 25 people. The man-day quota is shown in Table 5.
Foundation pouring and maintenance
Foundation formwork removal and backfilling
Work content: formwork removal, formwork collection and transportation, backfilling, and soiling. Staffing: 2 intermediate technicians, 2 junior technicians, a total of 4 people. The man-day quota is shown in Table 6.
Casting foundation cap, relocating side ditch, pillar protection 2.1.7.1
Work content:
Removal and backfilling of foundation formwork
Removal and backfilling of formwork
Casting foundation cap: installing model board, transporting materials, mixing, pouring, touching mold surface, and curing; I-11
Unit is man-days each
Unit is man-days each
Mortar-laying slabs: pulling wires, selecting slabs, leveling, slurry laying, filling, batching, manual mixing of mortar, mortar within 30m, and transportation of stone materials. Staffing: 1 intermediate technician, 2 junior technicians, a total of 3 people. The man-day quota is shown in Table 7.
Table 77
Casting foundation cap, relocating side ditch, pillar protectionCasting foundation cap
Relocating side ditch (mortar masonry)
Restore shoulder
Work day/place
Pillar protection
Concrete pillar
Mortar masonry slabs
Work day/m3
2.1.8 Earthing and soil abandonment
Work content: earthing, soil abandonment, manual lifting and transportation. Staffing: 1 intermediate technician, 2 junior technicians, a total of 3 people. The work day quota is shown in Table 8.
Table 8 Earthing and soil abandonment
Mechanical pole erection
Soil extraction within 50m
Every additional 50m
Work content: reverse the working vehicle, run, pole erection, return, and load. Transport distance within 50m
Staffing: 2 senior technicians, 3 intermediate technicians, 4 junior technicians, a total of 9 people. The workday quota is shown in Table 9.
Table 9 Mechanical pole
Gate bracket installation
Work content:
2. 1.10.1
Round pole pillar
Soft cross-beam pillar
Pre-configuration: pads, position adjustment, combination, ruler, adjustment, firmness; Steel pillar
GB/T19620—2004
Unit is man-day per cubic meter
Every additional 50m
Unit is man-day per piece
Conical pillar
Installation: Fix the crane, loosen the foundation nut, remove the wrapping, hoist, fix the foundation nut, move the manual crane. Staffing: 4 senior technicians, 8 intermediate technicians, 2 junior technicians, a total of 14 people, the man-day quota is shown in Table 10.
Quota/(man-day/group)
2. 1.11. 1
Gate bracket welding
Gate bracket installation
Gate bracket length/m
Manual installation
Work content: fixing ladder car, adjusting bracket, welding; zinc spraying, painting, transfer ≥9.5
Staffing: 1 senior technician, 4 intermediate technicians, 2 junior technicians, a total of 7 people. The man-day quota is shown in Table 11.
Gate bracket disassembly and assembly
Gate bracket welding
Work content: disassembling crane, loading, running, lifting, assembly. 2.1.12.2
Staffing: 3 senior technicians, 10 intermediate technicians, 2 junior technicians, a total of 15 people, the man-day quota is shown in Table 12.
Gate-shaped bracket disassembly and assembly
Mechanical installation
Unit is man-day per group
Unit is man-day per groupbZxz.net
GB/T19620—2004
Reinforced concrete pillars, steel column straightening and soft cross-pillar reinforcement 2.1.13.1
Work content:
Reinforced concrete pillar straightening: measuring limits, buried depth, straightening backfill layered compaction, soft cross-bar including anchoring and removal; steel column straightening: straightening, padding, tightening foundation nuts, fixing; pillar reinforcement: material transportation, stone washing, manual mixing, tamping, stone masonry, pouring, 2.1.13.2
Staffing: 3 senior technicians, 3 intermediate technicians, 4 junior technicians, a total of 10 people. The work day quota is shown in Table 13
Reinforced concrete pillars, steel pillar alignment and soft cross-pillar reinforcementReinforced concrete pillar alignment
General pillars
Soft cross-pillars
Work day/root
Backfilling of pillars and installation of horizontal slabs and bottom plates
Work content:
2. 1.14.1
Backfilling of pillars: backfilling and compaction;
Reinforcement of soft cross-pillars
Reinforcement of general pillars
Work day/place
Installation of horizontal slabs and bottom plates: transportation, trimming of pillar pits, leveling, measurement of limits, and fixing. 2.1.14.2
Staffing: 1 senior technician, 1 intermediate technician, 2 junior technicians, a total of 4 people. The work day quota is shown in Table 14.
Assembly of pillars
General pillars
Soft cross-columns
Work day/place
Work content:
Backfilling of pillars and installation of horizontal plates and bottom plates
Installation of horizontal plates
General pillars
Pre-assemble pillar arms: measurement, assembly, adjustment, on-site pre-assembly: soft cross-columns
Installation of bottom plates
Work day/piece
Installation of pillar arms: installation of clamps, installation of bases, installation of porcelain bottles, arm compression pipes, adjustment, and fixing. 2.1.15.2
Staffing: 3 senior technicians, 5 intermediate technicians, a total of 8 people. The work quota is shown in Table 15
Single-pressure pipe arm
Installation of beam slings, suspension base, station slings 2.1.16.1
Pillar assembly
Double-pressure pipe arm
Work content: receiving materials, manpower transportation, installation, adjustment, installation
Staffing: 2 senior technicians, 8 intermediate technicians, 2 junior technicians, a total of 12 people. The work day quota is shown in Table 16.
Install beam slings, suspension bases, station slingsBeam slings
Suspension bases
Steel column alignment
Man-day/root
Backfilling of anchor plates
Pulling pits
Man-day/unit
Unit is man-day per group
Install clamp bases
Unit is man-day per group
Station slings
Shoulder frame support cap installation
2. 1.17.1
2. 1.17.3
Work content: receiving materials, manpower transportation, measurement, installation, adjustment and reinforcement. Staffing: 3 senior technicians, 4 intermediate technicians, a total of 7 people: see Table 17 for the man-day quota.
Power supply line shoulder frame installation
Anchor compensation assembly and wire installation
Work content:
Shoulder frame support cap installation
Support cap installation
GB/T19620—2004
Unit is man-days per place
Wrist arm reinforcement
Anchor compensation assembly: receiving materials, inspection, pre-allocation, manpower transportation, installation of compensation equipment bracket, installation and adjustment of restriction pipe; wire installation: receiving materials, inspection, pre-allocation, manpower transportation, installation of wire, adjustment 2.1.18.2
Staffing: 1 senior technician, 1 intermediate technician, 2 junior technicians, a total of 4 people. The man-day quota is shown in Table 18.
Installation of wire anchor angle steel
Drilling and bolt installation in tunnel
Anchor compensation assembly and wire installation
Full compensation
Outside tunnel
Drilling and bolt installation in tunnel (mechanical) 2. 1.19. 1. 1
2.1.19.1.2
2.1.19.1.3
Percussion type
Pulling type
Pouring type
Inside tunnel
No compensation
Outside tunnel
Unit is working day per group
Installation of wire
Work content: transportation of materials and tools, power generation and lighting, drilling, dust removal, protection, bolt installation, tensile test of heavy-load anchor bolts. Staffing: 1 senior technician, 1 intermediate technician, 3 junior technicians, a total of 5 people. The work quota is shown in Table 19
Drilling and bolt installation in tunnels (mechanical) Table 19
$8mm~12 mm
Note: The numerical range in the table can be found in Appendix AA.2, 2.1.19.2
Drilling and bolt installation in tunnels (manpower) 2.1.19.2.1
2.1.19.2.2
2.1.19.2.3
Percussion
Pulling
Pouring
$12mm~16mm
$16mm~20mm
Unit is man-days per place
$>20mm
Work content: transportation of materials and tools, power generation and lighting, drilling, dust removal, protection, bolt installation, tensile test of heavy-load anchor bolts, staffing: 2 senior technicians, 3 intermediate technicians, 3 junior technicians, a total of 8 people. The man-day quota is shown in Table 20.
Drilling and bolt installation in tunnel (manpower) $8mm~12mm
12 mm~16 mm
$16 mm~20 mm
Unit is man-day per place
GB/T19620—2004
Elastic base installation in tunnel
2.1.20.1 Installation of elastic base in tunnel (mechanical) 2. 1.20.1.1
2. 1.20.1.2
2.1.20.1.3
Work content: lighting, pre-matching, installation of elastic base, adjustment. Staffing: 1 senior technician, 1 intermediate technician, 3 junior technicians, a total of 5 people. The man-day quota is shown in Table 21.
Elastic base
Elastic base installation in tunnel (manpower)
2.1.20.2.1
2.1.20.2.2
2.1.20.2.3
Installation of elastic base in tunnel (mechanical)
Anchor section joint
Work content: lighting, pre-matching, installation of elastic base, adjustment. Installation of locator bracket
Staffing: 2 senior technicians, 3 intermediate technicians, 3 junior technicians, a total of 8 people. The working day quota is shown in Table 22.
Elastic base
Installation of feeder and ground wire shoulder bracket inside and outside the tunnel
Installation of elastic base in tunnel (manpower)
Anchor section joint
Work content: receiving materials, manpower transportation, installation, and wrapping porcelain bottles. Installation of locator bracket
Staffing: 1 senior technician, 1 intermediate technician, 3 junior technicians, a total of 5 people. The working day quota is shown in Table 23.
Table 23 Installation of feeder and ground wire shoulder brackets inside and outside the tunnel
Locater measurement and pre-installation
Tunnel internal bracket
Tunnel external shoulder bracket
Work content: measurement, inspection, pre-installation, lighting. Tunnel internal bracket
Staffing: 1 senior technician, 1 intermediate technician, 3 junior technicians, a total of 5 people. The work day quota is shown in Table 24.
Table 24 Positioner measurement and pre-configuration
2.1.23 Soft cross-over installation
2. 1.23.1
Inside the tunnel
Outside the tunnel
Work content: measurement, inspection, prefabrication, marking, installation, adjustment of ground wire
Unit is man-days per place
Elongated base installation
Unit is man-days per place
Elongated base installation
Unit is man-days per group
Tunnel external shoulder frame
Unit is man-days per group
Staffing: 1 senior technician, 1 technician, 7 senior technicians, 7 intermediate technicians, a total of 16 people. The man-day quota is shown in Table 25.
Small station reinforced concrete
Column single load-bearing cable
Station steel column
Single load-bearing cable
Double load-bearing cables
5~8 tracks
Note: For relevant regulations, see Appendix AA.8.
Rigid busbar installation
Table 25 Soft crossbar installation
Messenger cable and
Upper fixed
Rope prefabrication
Lower fixed
Rope prefabrication
Installation of Messenger cable Upper fixed rope
Work content: Anchor length measurement, busbar pre-assembly, installation, grounding clamp installation, electrical grease application GB/T19620—2004
Unit is man-day per group
Fixed rope
Staffing: 1 technician, 6 senior technicians, 3 intermediate technicians, 5 junior technicians, a total of 15 people. The man-day quota is shown in Table 26.
Installation of rigid-flexible transition
Anchor section measurement and prefabrication
Installation of rigid busbar
Installation of rigid busbar
Man-day/(line·km)
Work content: installation and adjustment of electrical connections. 56.0
Installation of grounding wire clamp
Work items/place
Work/(line·km)
Staffing: 1 technician, 6 senior technicians, 3 intermediate technicians, 5 junior technicians, a total of 15 people. The man-day quota is shown in Table 27.
Structural prefabrication
Erection of load-bearing cables
Return.
Installation of rigid-flexible transition
Insulation of ground wire
Insulator cleaning
Unit is man-days per place
Installation of electrical connection
Work content: preparation for stringing, cable drum, reverse track of stringing vehicle, operation, temporary anchoring, laying out wire, measuring the degree of slack, temporary anchoring, inspection, Staffing: 2 technicians, 8 senior technicians, 8 intermediate technicians, a total of 18 people. The man-day quota is shown in Table 28.
Table 28 Erection of load-bearing cables
Inside the tunnel
Outside the tunnel
2.1.27 Installation of suspension strings
Single load-bearing cables
2.1.27.1 Work content: measurement, calculation, prefabrication, installation. 2.1.27.2
Double-bearing cable
Staffing: 2 senior technicians, 4 intermediate technicians, a total of 6 people. The man-day quota is shown in Table 29.
Single-bearing cable
The unit is man-day per kilometer
Inverted saddle
Double-bearing cable