HG/T 2147-1991 Rubber profiling calender

Basic Information

Standard ID: HG/T 2147-1991

Standard Name: Rubber profiling calender

Chinese Name: 橡胶压型压延机

Standard category:Chemical industry standards (HG)

state:in force

Date of Release1991-08-19

Date of Implementation:1992-01-01

standard classification number

Standard ICS number:Chemical technology>>71.120 Chemical equipment Rubber and plastics industry>>83.200 Rubber and plastics industry equipment

Standard Classification Number:Chemical Industry>>Chemical Machinery and Equipment>>G95 Rubber and Plastic Machinery

associated standards

Publication information

other information

Introduction to standards:

HG/T 2147-1991 Rubber Profile Calender HG/T2147-1991 Standard Download Decompression Password: www.bzxz.net

Some standard content:

Chemical Industry Standard of the People's Republic of China
HG/T2147-91
Rubber Profiling Calender
Published on August 19, 1991
Ministry of Chemical Industry of the People's Republic of China
Standard Exchange Network m
Implementation on January 1, 1992
Chemical Industry Standard of the People's Republic of China
Rubber Profiling Calender
1 Subject Content and Scope of Application
HG/T2147--91
This standard specifies the basic parameter technical requirements, safety requirements, test methods and inspection rules of rubber profiling calender (hereinafter referred to as profiling machine).
This standard applies to calenders used for profiling rubber shoe outsoles, uppers and welts. 2 Reference standards
GB1184
GB6388
Packaging storage and transportation pictorial signs
Shape and position tolerances Provisions for unmarked tolerances Transport packaging shipping and receiving signs
Chilled cast iron rollers
GB9709
ZBG95010
General technical conditions for painting of rubber and plastic machinery General technical conditions for appearance of rubber machinery
HG5-1541
General technical conditions for packaging of rubber machinery
HG5-1S43
JB8 Product label
3 Basic parameters
The basic parameters of the press machine shall comply with the provisions of the following table: Roll size
Roll surface width
Roll maximum linear speed
Note: 1) A 5% variation is allowed for the diameter of 230mm. 4 Technical requirements
Minimum power of main motor
Maximum profile thickness
4.1 The profile forming machine shall comply with the requirements of this standard and be manufactured in accordance with the drawings and technical documents approved through the prescribed procedures. 4.2 The fixed roller of the press is a chilled iron roller, and its mechanical properties and technical requirements shall comply with the provisions of GB9709. 4.3 The movable roller of the molding machine is a steel roller, and its mechanical properties shall meet the following requirements: tensile strength shall not be less than 560N/mm2, service strength shall not be less than 280N/mm, and surface hardness shall not be less than the requirements of HB180. 4.4 The roughness Ra value of the working surface of the roller shall not be greater than 1.6μm. The standard approved by the Ministry of Chemical Industry of the People's Republic of China on August 19, 1991 and implemented on January 1, 1992 is HG/T2147--91. 4.5 The bearing surfaces of the slide grooves of the roller bearings installed on the left and right turntables of the molding machine shall be on the same axis, and their flatness shall comply with the requirements of the 7th grade tolerance value in Appendix 1 of GB1184.
4.6 The bearing holes of the left and right frames of the type machine should be on the same axis, and their coaxiality should comply with the provisions of the 8th grade tolerance value in Appendix 4 of GB1184.
4.7 The total axial clearance between the two end faces of the saw shaft neck of the type machine and the end face of the j bearing should be within the range of 0.7~1.5mm. 4.8 The rotary plate of the press machine should rotate flexibly, and the locking device should work reliably. 4.9 The heating and cooling system must be subjected to a pressure resistance test, and the test pressure shall not be lower than 1.5 times the working pressure, and the pressure shall be maintained for 5 minutes without leakage.
The pipeline of the lubrication device should be cleaned, unobstructed, and without leakage. The motor power of the press machine when it is running idle shall not be greater than 15% of the rated power. When the press machine is running idle, the temperature rise of the roller bearing shall not exceed 20°C, and there shall be no sudden rise. 4.13
When the press machine is running under load, the temperature rise of the roller bearing shall not exceed 40°C. 4.14
The appearance quality of the press machine shall comply with the provisions of HG5-1541. The paint quality of the press machine shall comply with the provisions of ZBG95010. 4.15
5 Safety requirements
5.1 Emergency brake control devices shall be installed at the front and rear of the press machine. After braking, the roller shall not continue to rotate more than 1/4 of the circumference of the drum. 5.2 The press machine shall run smoothly. No abnormal vibration: The noise sound pressure level during operation shall not be greater than 80dB (A). 5.3 The transmission parts of the press machine exposed outside the machine shall have protective devices. 6 Test method
Idle running test
After the whole machine passes the general assembly inspection, an idle running test of no less than 2h (each movable roller runs for 0.5h respectively) shall be carried out. 6.1.1
6.1.2. The following items shall be checked in the idle running test: 8.
Measure the linear speed of the roller;
According to the provisions of Article 4.8, check the switching flexibility of the turntable and the reliability of the locking device; check the motor power value:
d., check the roller bearing temperature according to the provisions of Article 4.12: e.
Check the reliability of the installation device according to the provisions of Article 5.1: Measure the noise level with a sound level meter, which shall comply with the provisions of Article 5.2. 6.2 Load running test
The load running test can only be carried out after the idle running test is passed. 6.2.1
The load operation test time shall not be less than 2h, and the following items shall be checked: 6.2.2
The heating and cooling piping system shall not leak under working pressure: The overflow of roller bearing shall be measured with a point overflow meter, which shall comply with the provisions of Article 4.13: The noise sound pressure level shall be measured with a sound level meter, which shall comply with the provisions of Article 5.2. 7 Inspection rules
7.1 Factory inspection
7.1.1 Each product must be inspected before leaving the factory. 7.1.2. The factory inspection shall be carried out in accordance with 6.1, 4.14 and 4.15 and shall comply with their provisions. 7.1.3 Each product shall be inspected and qualified by the quality inspection department before it can be shipped out. When it leaves the factory, it shall be accompanied by the product instruction manual and quality certificate, etc.
Standard Exchange Network m
ccce7.2 Type inspection
HG/T2147-91
7.2.1 Type inspection shall be carried out in accordance with the requirements of the standard and shall comply with its provisions. 7.2.2
Type inspection is required in any of the following situations: a., trial production and identification of new products or old products transferred to the factory for production; when the product has major changes in design, structure, material and process; b.
When the product has been discontinued for more than 3 years and is resumed; during normal production, at least one unit shall be inspected each year. When the random inspection fails, two more units should be sampled: if there is still one unit that fails, the batch of products should be inspected one by one after clarifying the reasons.
8 Marking,
Packaging, transportation, storage
Each machine should have a product label fixed in a conspicuous position. The label type, size and technical requirements should comply with the provisions of JB8 8.1
8.2 The basic content on the product label should include: s.
Manufacturer name and trademark;
Product name;
Product model or mark:
d.·Manufacturing date and product number (or production batch number). 8.3 The packaging quality of the machine should comply with the provisions of HG·5--1543. 8.4 The packaging and transportation labels of the machine should comply with the provisions of GB191 and GB6388. 8.5 The machine should be stored in a dry and ventilated place before installation to avoid moisture. Rain protection measures should be taken for outdoor storage. 9
Under the condition that the user complies with the requirements of transportation, storage, installation and use, and unpacks and accepts the product within 3 months after arrival, the manufacturer shall bear the warranty period of 18 months from the date of arrival of the product. Additional notes:
This standard is proposed by China National Chemical Equipment Corporation and is under the jurisdiction of the Rubber Machinery Sub-Technical Committee of the National Rubber and Plastic Machinery Standardization Technical Committee. This standard was drafted by Guangdong Zhanjiang Hui Machinery Factory and the drafter of this standard was Gu Jianming.
Standard Exchange NetworkwwW.bzxz.Net
0mFree download of various standard industry information
People's Republic of China
Chemical Industry Standards
Rubber Profile Calender
HG/T2147-91
Chemical Industry Standards Editorial Department
Standardization Research Institute of the Ministry of Chemical Industry)
Postal Code: 100013
Printing Standardization Research Institute of the Ministry of Chemical Industry
Copyright reserved. No reproduction allowed
Number of characters on the print head: 6000
Format: 880×12301/16
First printing in August 1992
First edition in July 1992
Number of copies: 1-300
Standard Authorization Network.520:00m