HG 20557.3-1993 Quality Assurance Procedure for Process System Professional Engineering Design

Basic Information

Standard ID: HG 20557.3-1993

Standard Name: Quality Assurance Procedure for Process System Professional Engineering Design

Chinese Name: 工艺系统专业工程设计质量保证程序

Standard category:Chemical industry standards (HG)

state:in force

Date of Release1994-08-03

Date of Implementation:1996-03-01

standard classification number

Standard ICS number:71.010

Standard Classification Number:>>>>P7 Chemical Industry>>Comprehensive Chemical Industry>>G04 Basic Standards and General Methods

associated standards

Publication information

other information

Introduction to standards:

HG 20557.3-1993 Quality Assurance Procedure for Process System Professional Engineering Design HG20557.3-1993 Standard Download Decompression Password: www.bzxz.net

Some standard content:

Industry Standards of the People's Republic of China
Regulations on the Management of Process System Design
HG20557-93
Main Editor: Process System Design Technology Center of the Ministry of Chemical Industry Approval Department: Ministry of Chemical Industry
Implementation Date: October 1994
Chemical Engineering Design Standards Compilation Center
Beijing 1994
Quality Assurance Procedures for Professional Engineering Design of Process System
HG20557.3
Compiled by: China Chengsong Chemical Engineering Corporation Approval Department: Ministry of Chemical Industry
Implementation Date: October 1994. [1 Document Management
1. Acceptance of the relevant documents and instructions
1.11 The person in charge of the profession shall submit the design and network diagram to the professional or department that provides the conditions, distribute them to relevant personnel, and establish a project file for the management department to consult. 1.1.2 The person in charge of the specialty shall ensure that all the accepted conditions must be reviewed and signed by the review personnel of the specialty or department that proposed the conditions.
1.1.3 The person in charge of the specialty shall regularly check the accepted documents to ensure that the relevant personnel use the latest version of the conditions (especially important when preparing the construction version). 1.1.4 The person in charge of the specialty shall manage and distribute all the accepted documents in accordance with the "Regulations on the Management of Design Materials of Professional Work Shoes" (HG20557.593). 1.2 Proposed conditions
[.2.1 The proposed conditions shall be managed by the person in charge of the specialty. The person in charge of the specialty must ensure that the proposed conditions have been reviewed and signed according to the planned guarantee procedures. 1.2.2 The person in charge of the specialty shall keep the original documents compiled by the specialty. 1.2.3 In addition to keeping the original in the archives, the person in charge of the specialty shall keep a copy of each and every version of the proposed document and send it to a single archive together with the drawings and materials. 1.2.4 The professional designer of the process system shall prepare the letters related to the project and send them to other professionals. Before sending them out, the professional person in charge shall directly check and sign on the documents. 1.2.S The professional person in charge shall review the documents according to the situation. 19
2 Responsibilities of each level
2.! The authority of the professional design of the process system at all levels is divided into three levels in order to ensure the quality. 2.1.1 Design and compilationWww.bzxZ.net
The design and compilation level shall be approved by the professional designer of the process system. 2.1.2 Proofreading
The proofreading level shall be approved by the professional designer with a higher level of professional knowledge and less work experience. The proofreading qualification shall be approved by the unit.
2.1.3 Review:
The review shall be conducted by the process system professionals with official review qualification approved by the entity. If necessary, the professional person in charge, laboratory director or chief engineer with review qualification shall be responsible (see the quality assurance review procedure for details) 2 Division of quality assurance work
For any calculation or document, one person is allowed to perform more than one quality assurance work. For example, a plan reviewer cannot be a designer, and a document reviewer cannot be a checker. 20
3.1.1 Design development report,
3.1.2 Engineering design basic number.
3.1.3 User regulations and surface opinions.
3 Design regulations
3.1 Acceptance conditions
3.2 Preparation, review and approval
3.2.1 Take the preparation of "Noise control design regulations reduction requirements" as an example to explain as follows: 3.2.1.1 "Noise control design regulations preparation requirements" shall be prepared by the professional noise control design personnel of the process system. 3.2.1.2 After the preparation of "Noise control design regulations preparation requirements", the professional person in charge of the process system shall send them to the technical management department and other relevant departments for registration.
3.2.1.3 After comprehensive review opinions from all aspects, the professional noise control design personnel of the process system shall sign on the document, and it shall be checked and signed by the review personnel. 3.2.1.4 "Noise control design regulations preparation requirements" shall be submitted to the design manager, and the design manager shall solicit user opinions, and then the original design personnel shall incorporate the correct opinions. .2.1.5 The director of the department or the chief engineer shall review the final document and confirm that all his correct opinions have been conveyed before signing. 3.2.1.6 The final "Noise Control Design Specifications" shall be sent by the professional person in charge to the design manager for approval and signature: When user confirmation is required, the design shall be sent to the end user for approval and signature, and then the design manager shall issue this document. 3.2.1 The design specifications for insulation, coatings and material control specified in the specification shall be confirmed by the professional review or audit personnel of the process system: The design specifications for containers, heat exchangers and special equipment professionals for the common material system in the device shall also be confirmed by the designated professional review or audit personnel of the process system: 3.2.3 The design specifications are important design documents, so modifications should be kept to a minimum. Most modifications are made through change notification. For any modification proposed by the process system professionals, the modification instructions shall be prepared and submitted to the user for record. 21
4 Calculation
The calculation of all process system professionals shall be based on the relevant methods and calculation formulas approved by the company (institute). When the above-mentioned books do not include the required information, the technical management department may organize relevant professionals to propose, collect the process system professionals, and the technical management department shall organize discussions, apply and approve them to ensure the quality of calculation work.
4.1 Acceptance of documents
Design certification report.
Engineering design basic data.
Documents published by chemical process professionals,
Construction equipment layout drawings.
4.1.5 Material preparation summary.
Pipeline wall table.
Pipeline category (including pipeline design, pipeline materials, pipeline mechanics and other disciplines) design over-determination summary table and reference control chart.
Process equipment table.
Material balance:
Design compliance
4.2 Calculation types
Key calculations include such contents as
4.2.1.1 NPSH and pump pressure calculation:
4.2.1.2 Pressure difference of compressor:
4.2.1.3 Overload protection; calculation of safety valve (drying rupture disc) and safety vent main pipe: 4.2.1.4 Calculation of thermocouple system,
4.2.2 Standard calculations include the following contents:
4.2.2.1 Partial calculation of flow elements of control valves, 4.2.2.2 Water calculation of pipelines +
4.2.2.3 Tower top pipeline calculation,
4.2.3 Any standard calculation can be checked or approved by designated process system professionals as key calculations. This provision should be made at the beginning of each project. 4.3 Preparation
Calculations shall be prepared and compiled by professional process system designers. These calculations shall be consistent with the procedures specified by the company (or company) and shall use standard formats as much as possible. 4.4 Review and Audit
4.4.1 The preliminary results of key calculations shall be reviewed by designated process system professionals and checked to see if they meet the requirements of the project.
4.4.2 When necessary, the final results of key calculations shall be reviewed and signed by the director of the department or the chief engineer. 4.4.3 The final standard calculations shall be reviewed and signed by designated process system professionals. When necessary, the control and flow calculation data sheets shall be reviewed and signed by the process system designers. 4.5 Calculation Modifications
4.5. The modifications made shall be reviewed by the process system designers and the scope of the modifications shall be clearly marked.
4.5.2 All modifications to the chain calculations shall be replaced and signed by the designated system design personnel. 4.5.3 The professional person in charge shall determine whether the standard calculation modification needs to be checked, and all the checked ones shall be signed.
Design commencement report.
5 Pipeline instrument flow chart (diagram)
5.1 Acceptance materials
Engineering design basic data,
5.1.3 Material service summary:
Coordination procedures.
Process equipment table:
User's vision and instructions:
Process published documents:
Various versions of towers, maintenance and efficiency data sheets, heat exchanger training tables.
Machine multiplier table.
Operation requirements.
Process drawing