HG/T 20704.3-2000 Working procedures for the design phase of pump engineering

Basic Information

Standard ID: HG/T 20704.3-2000

Standard Name: Working procedures for the design phase of pump engineering

Chinese Name: 机泵专业工程设计阶段的工作程序

Standard category:Chemical industry standards (HG)

state:in force

Date of Release2000-11-22

Date of Implementation:2001-06-01

standard classification number

Standard ICS number:71.010

Standard Classification Number:Engineering Construction>>Raw Materials Industry, Communications, Broadcasting Engineering>>P72 Petrochemical, Chemical Engineering

associated standards

Publication information

other information

Introduction to standards:

HG/T 20704.3-2000 Working procedures for the design phase of pump engineering HG/T20704.3-2000 standard download decompression password: www.bzxz.net

Some standard content:

Working procedures for the engineering design phase of pump specialty HG/T20704.3--2000
Subject content and scope of application
This standard specifies the working steps and working procedures for the two main design phases of pump specialty. Applicable to design management personnel The design working procedures of pump specialty are divided into two stages: preliminary design and engineering design. 2
Preliminary design phase
Accept relevant professional conditions and conduct condition review. Study the selection issues of key pumps, preliminarily select the types of main pumps, and prepare preliminary engineering design regulations.
Carry out pump selection, prepare pump data sheets or cooperate with chemical process professionals to prepare process equipment sheets, and propose the expected energy consumption of pumps.
When necessary, prepare inquiry technical documents such as brief purchase instructions for pump pre-inquiry. Propose preliminary design conditions to relevant professionals. Prepare preliminary design instructions.
3 Engineering Design (Construction Drawing Design) Phase
The design procedure of the engineering design (construction drawing design) phase is detailed in the design work procedure diagram, and the relevant instructions are as follows: 3.0.1 Tasks
The work of this specialty runs through the entire process of engineering construction. The main work is to compile engineering design 287
regulations around the purchase of pumps, compile technical documents for the purchase of pumps (inquiry, ordering), review quotation documents, participate in coordination meetings, and review the ACF and CF drawings and materials of manufacturers (commercials).
3.0.2 Accept the design conditions of relevant specialties and conduct reviews. 3.0.3 Compilation of Engineering Design Regulations
The engineering design regulations are compiled mainly by this specialty. The relevant chapters will comprehensively incorporate the opinions of the process, system, pipeline, instrumentation, electrical, material, inspection and other departments. Therefore, the first draft compiled by this specialty should be submitted to the above-mentioned specialties and relevant departments for review in accordance with the requirements of the design quality assurance procedure. 3.0.4 Preparation of pump procurement (inquiry, order) technical documents Pump procurement (inquiry, order) technical documents usually include: general technical regulations for equipment, equipment (inquiry, order) purchase order/technical specifications, data sheets, etc.
Equipment purchase order and/or technical specifications and data sheets are prepared by this specialty according to the opinions or conditions of the process, system, pipeline, instrumentation, electrical, material, inspection and procurement departments. The equipment purchase order and/or technical specifications are also submitted to the above-mentioned relevant disciplines and departments for review in accordance with the requirements of the design quality assurance procedure; the inquiry technical documents are submitted to the design manager for delivery to the procurement department after being reviewed by this specialty.
3.0.5 Review of quotation technical documents
Reviewing the quotation technical documents of the manufacturer (commercial) is an important task of this specialty. This specialty will comprehensively solicit the review opinions of all relevant disciplines and make technical evaluations of the quotations. When several manufacturers (commercials) make quotations at the same time, this specialty should be responsible for completing the technical review form and review opinions of the quotations, as well as the recommendations for selecting the purchasing manufacturer (commercial). The technical review form and review opinions shall still be reviewed according to the requirements of the design quality assurance procedure and then submitted to the design manager for sending to the purchasing department. 3.0.6 Participation in the coordination meeting
A manufacturer (commercial) coordination meeting (VCM) is required for key pumps. This meeting is an important meeting to discuss the design, material selection, manufacturing, inspection and other related issues of the pump with the manufacturer (commercial). The meeting is mainly prepared by this profession, and the whole process of the meeting is participated in. Before the meeting, the detailed agenda of the meeting (technical part) shall be prepared by this profession. Records shall be taken during the meeting, and the compilation of the minutes of the meeting shall be completed (technical part). For general pumps, there is no need to form a separate minutes, and the discussion results of relevant technical issues only need to be included as a supplementary clause in the order contract. 3.0.7 Preparation of Order Data Sheet
The order data sheet is completed by supplementing and modifying the quotation information, data and minutes of the coordination meeting (VCM) of the manufacturer (commercial) on the basis of the inquiry data sheet. After verification, it is submitted to the design manager and sent to the procurement department. The order data sheet is an important part of the technical attachments of the order contract. 3.0.8 Review of Pre-confirmation (ACF) Drawings and Materials Pre-confirmation (ACF) drawings and materials are the drawings and materials provided in advance designed and drawn by the manufacturer (commercial) according to the requirements of the order technical documents. The drawings and materials have been signed by the relevant personnel (design, verification, and review) of the manufacturer (commercial). The review of ACF drawings and materials is the responsibility of this specialty, which summarizes the review opinions of this specialty and the system, layout, pipeline, pipe machine, pipe material, instrumentation, electrical, civil engineering, material, inspection department, etc. The review opinions are submitted to the design manager and sent to the procurement department and the manufacturer (commercial). The manufacturer (commercial) supplements and modifies the final confirmation (CF) drawings and materials accordingly. 3.0.9 Review of Final Confirmation (CF) Drawings and Materials Final Confirmation (CF) drawings and materials are the final drawings delivered by the manufacturer (commercial) to the production workshop for processing and manufacturing. For the sake of prudence, the design (purchase) party should review them again to ensure that the drawings and materials of the manufacturer (commercial) fully meet the order requirements. Finally, they will be sent to all relevant professionals as the final condition. 3.0.10 Review of product test records and certificates of conformity Product test records are documents that provide objective evidence of the results achieved by the manufacturer (commercial) at each major stage of product processing and manufacturing, based on relevant standards or specified test methods. The certificate of conformity is a document provided by the manufacturer (commercial) to prove that its products meet the specified requirements. 4 Appendix
Machine pump professional work procedure chart
Design manager
Work report and its attachments
Equipment standard
NESH table
Only table professional
Only table design regulations
Electrical professional
Hazardous area division diagram
Material professional
Engineering material construction and use regulations
Related engineering standards and regulations|| tt||Camp material major
Pipe material classification table
Pipe material and
Floating paint design regulations
Installation layout
Standards Department
Latest edition
Professional standard frequency
Design case Yangshi
Design manager-
User (owner)
Engineering design regulations
Dream plus thing theft
Relevant majors
Limited design manager--
Relevant majors
Expected machine pump reliability
E consumption summary table
Participate in the investigation
Relevant majors
Stock planning manager-
Purchasing department
Inquiry technical documents
Root expansion technology
Benzene transformers
Purchasing department
Design manager
Design Design manager
Deception department
Manufacturer quotation
Technical document review
Table and market evaluation opinions
Design manager
Purchase department
Related professional
(VCM) minutes (technical part)
Modified or updated
Documents and data sheets
Prepare YCKbzxZ.net
Quotation technical documents
Participate in quotation review
with beauty majors
detailed revision
NCM details
topic
relevant majors
fishing preparation and participate in
VCM) coordination meeting
agree on the notice of opening VCM
Purchasing department one
design manager
design manager—
purchasing department||t t||Order data
Design manager
Purchasing department
ACF paper width
Review opinion
ACF national data
ACF drawing materials
Design manager
Purchasing department
Add review to
CF drawing materials
Related majors
Design manager-
Purchasing department|| tt||CF drawing materials
Opinions
Cr national paper materials
CF drawing compilation research
Purchasing department
F drawing installation
Related majors
Design manager--
Related majors
CF drawing continuation materials
Design integration
Purchasing department
Design manager
Purchasing post, product (owner
Prepare for installation,
Maintenance and other technical documents
(General contracting)
City inspection product test
Already qualified
Product test record
Certificate
Design manager
Purchasing department
Note: ①General record does not need to hold VCM, so the process of preparing and participating in the coordination meeting (VCM) can be omitted. ② Review the CF drawings. This process is only carried out when there are comments.