SY 4032.6-1993 Petroleum Construction Project Quality Inspection and Assessment Standard Communication Engineering (Installation of Urban Telephone Exchange Equipment)

Basic Information

Standard ID: SY 4032.6-1993

Standard Name: Petroleum Construction Project Quality Inspection and Assessment Standard Communication Engineering (Installation of Urban Telephone Exchange Equipment)

Chinese Name: 石油建设工程质量检验评定标准 通信工程(市内电话交换设备安装工程)

Standard category:Oil and gas industry standards (SY)

state:in force

Date of Release1993-11-26

Date of Implementation:1994-05-01

standard classification number

Standard ICS number:75.010

Standard Classification Number:>>>>P7 Engineering Construction>>Industrial Equipment Installation Engineering>>P92Telecommunication Equipment Installation Engineering

associated standards

alternative situation:SYJn4032-88

Publication information

other information

Publishing department:China National Petroleum Corporation

Introduction to standards:

SY 4032.6-1993 Petroleum Construction Project Quality Inspection and Assessment Standard Telecommunication Engineering (Installation of Urban Telephone Exchange Equipment) SY4032.6-1993 Standard Download Decompression Password: www.bzxz.net

Some standard content:

Standard for Quality Inspection and Evaltation of Petroleum Construction EngineeringTelecommunication Engineering(Local Switching Equipment Installing Engineering)SY 4032.6--93
Text description
Petroleum Industry Press
1993·Beijing
Pre-construction inspection
Iron processing engineering
Large iron frame and main distribution frame installation engineering
Electric walkway installation engineering
Cable trough installation engineering·
Automatic switch and machine installation engineering
Cable laying and bundling engineering·
Comprehensive cable core wire engineering
Scrape, support, wind and clamp cable core wire engineering
Welding jumper engineering·
Signal system installation engineering
DC power line installation engineering in computer room
Automatic switch frame Ming'an Installation project
Equipment marking project
Key inspection, adjustment and installation project·Power-on test project
Other test projects
(6)
: Revision notes
According to the requirements of the notification of China National Petroleum Corporation (92) Zhongyou Ke Zi No. 66: SY4032.6-93 "Petroleum Construction Project Quality Inspection and Assessment Standard Communication Engineering (City Telephone Exchange Equipment Installation Project)" edited by China National Petroleum and Natural Gas Pipeline Power Communication Engineering Company and participated in the compilation of the Engineering and Technology Research Institute of China Shipu Natural Gas Corporation was approved and issued by China National Petroleum and Natural Gas Corporation on November 26, 1993 (93) Zhongyou Ji Zi No. 764.
During the preparation process, the staff followed the relevant national policies and conducted a relatively extensive investigation and research, carefully summarized the practical experience of the quality inspection and evaluation of the installation of urban telephone exchange equipment in my country, and widely solicited the opinions of relevant units, discussed and revised repeatedly, and finally reviewed and finalized it in conjunction with relevant units by the Infrastructure Engineering Bureau of China National Petroleum Corporation. This standard is divided into 18 chapters and 3 appendices, and the main contents include general principles, pre-construction inspection and iron processing engineering, large-scale iron frame main distribution frame installation engineering, cable walkway installation engineering, cable trough installation engineering, automatic exchange and machine installation engineering: laying and bundling cable engineering, braiding cable core wire engineering, scraping, welding, winding, clamping cable core wire engineering, so welding jumper engineering, signal system installation engineering: computer room DC power line installation engineering, automatic exchange rack lighting installation engineering, equipment marking engineering, machine key inspection, adjustment and installation engineering, power-on test engineering, other test engineering, installation and electrical performance indicators of quality inspection and evaluation.
Since SYJn4024--88 "Standard for Quality Inspection and Assessment of Petroleum Engineering Construction" has been revised, this standard has also been modified and supplemented on the basis of the original SYJn4032-88.
In order to facilitate the relevant personnel of large-scale construction, quality inspection and other relevant personnel to correctly understand and implement the provisions of the standard, the drafters of this standard have compiled the provisions in accordance with the unified requirements of the state for the compilation of standard provisions and normative provisions, and in the order of chapters, sections and articles of the main text for reference.
It is hoped that all units will seriously summarize experience and accumulate information in the process of implementation in combination with engineering practice. If any amendments and supplements are found, please send your opinions and relevant information to the Pipeline Power Communication Engineering Company of China National Petroleum Corporation, Langfang City, Hebei Province (Postal Code: 102849) and the Standardization and Chemical Research Office of the Engineering Technology Research Institute of China National Petroleum Corporation, No. 40 Jintang Road, Tanghuo District, Tianjin (Postal Code: 300451) for reference in future revisions.
China Petroleum and Natural Gas Pipeline Power Engineering Company November 1993
2.1.1 (Added personal text)
2 Pre-construction inspection
2.1 Basic items
This article is compiled based on Article 2.1.1 of YDJ37-81 "Technical Specifications for Construction and Acceptance of Urban Telephone Exchange Equipment Installation Project". Complete machine room building conditions are a prerequisite for the construction unit to enter the construction site. If the machine room building is not completed or does not meet the machine room installation requirements, it will often bring difficulties to normal construction. Cross-operation of the previous processes will directly affect the construction progress, construction quality and personal safety of construction personnel. Therefore, before construction, the entire machine room and exchange room building conditions should be surveyed and inspected on site to ensure the smooth start of the project. 2.1.2 (Added Article)
This article is compiled based on Article 2.2.1, Article 2.2.2 and Article 2.2.3 of YDJ37-81.
The quality of equipment and instruments is an important prerequisite for ensuring the quality of construction and communication. Therefore, all equipment and instruments used in construction should be inspected and checked before the project starts. All equipment and instruments that do not meet the quality standards shall not be used in the project to prevent potential accidents.
3 Iron processing engineering
3.1 Basic items
, 1.1 (Reserved articles of Article 7.1.1 to Article 7.1.3 of the original standard) This article is compiled according to Article 2.1, 1: Article 2.1.3 and Article 2.1, 4 of the "Wired Communication Equipment Installation Process Operation Procedure". Iron processing is an important process in the installation of the machine room, and the quality of iron processing will affect the overall installation of the entire machine room. Therefore, the processing company shall check whether the material quality and specifications meet the design requirements. Materials that are severely rusted, cracked, angle steel is not at right angles, fan steel width is unequal, and affect strength but cannot be corrected shall not be used. The eyelets of processed iron parts should be straight and the size should be correct, otherwise it will cause difficulties in the assembly of the iron frame. 3.2 Allowed partial items
3.2.1 (Original standard Article 7.1 (Reserved Article 4) This article is compiled based on the content of Article 2.1.2 of the "Wired Communication Equipment Installation Process Operation Specifications".
The allowable deviation listed in this article is the indicator specified in YD37-81. 2
4 Large iron rack and main distribution frame installation project
4.1 Basic items
4.1.1 (Added articles)
This article is compiled based on Article 3.1.1, Article 3.1.3, Article 3.1.4, Article 3.2.1, Article 3.2.4 and Article 3.2.5 of YDJ37-81. The iron rack should be installed straight and firmly, because it is used to fix each rack and various rack inlet and outlet lines. The process level of the rack installation can directly reflect the aesthetics of the entire machine room. From the perspective of anti-sales: The firmness of the iron rack installation is The key point is that in addition, the screws at the connection between the ground wire and the iron frame should be tightened to ensure good electrical contact between the iron parts to ensure good grounding. 4.1.2 (Amendments to Articles 7.4.1 and 7.4.2 of the original standard) This article is compiled based on Articles 3.3.1 and 3.3.2 of YDJ37-81. The main distribution frame is used for the collection and connection of audio cables in the computer room. The installation should be neat and firm, and the installation position of the jumper ring must not be reversed.
4.2 Allowable deviation items
4.2.1 (Amendments to Articles 7.4.4 and 4.5 of the original standard) This article is compiled based on Articles 3.2.1 and 3.2.2 of YDI37-81. The allowable deviations listed here are the indicators specified in YDJ87-81. 3
5 Cable walkway installation Engineering
5.1 Basic Project
5,1,1 [Reservation of Article 11.2.1 and Article 11.2.2 of the original standard. This article is compiled based on Article 4.1.1 and Article 4.1.2 of DF37-81. When the rack in the room uses the walkway to collect the incoming and outgoing lines of each rack to the distribution frame for handover. Therefore, the installation of the walkway requires neatness and firmness, and the position deviation of the cable walkway should be within ±50mm. The installation of the horizontal iron in the pre-rack should mainly meet the cable bending so that the straight cable will not sink. The specific position depends on the cable downline. 5.1.2 (Added Articles)
This article is compiled based on Article 4.1.3, Article 4.1.4, Article 4.1.5, Article 4.1.6, Article 4.1.8 and Article 4.1.9 of YDJ37-81. The installation of vertical walkways and horizontal walkways should be firm and straight. For safety reasons, the vertical walkways through the building holes should be reinforced with iron frames at the room, and the walls should be reinforced with the walls, and the supports should be firmly installed.
5.2 Supplementary allowable deviation items
5.2.1 (The revised article of Article 11.2.6 of the original standard) This article is compiled based on Articles 4.1.1 and 4.1.3 of YDJ37-81.The allowable deviations listed in the article are the indicators specified in Y37-1. 4
6 Cable track installation project
6.1 Basic items
6.1.1 (the reserved items of Article 7.3.1 of the original standard) This article is compiled based on Articles 4.2.1, 4.2.2 and 4.2.3 of YDJ37-81.
The groove installation should be neat and firm, and the groove deformation caused by transportation or other reasons should be corrected by knocking, so that the groove side and the bottom surface are perpendicular to each other, so that the groove after installation can be placed smoothly and meet the process requirements. 62 Allowable deviation items
6.2.1 (the reserved items of Article 7.3.2 and Article 7.3.3 of the original standard) This article is compiled based on Articles 4.2.3 and 4.2.4 of YD13781. The allowable deviations listed in this article are the indicators specified in the YDJ37-81 construction specifications. 5
7 Automatic switch and machine installation project
7 Basic itemsWww.bzxZ.net
7.1.1 (Added articles)
This article is compiled based on the contents of Article 5.1.1, Article 5.1.2, Article 5.2.1 and Article 5.2.2 of YDJ37-81.
There are a large number of step-by-step switch racks installed, and the net distance between the rack and the column and between the racks should comply with the provisions of the construction drawings to avoid excessive accumulation of errors. The rack should be installed firmly and neatly in accordance with the process requirements. 7.1.2 (Reserved articles of Article 7.5.1 and Article 7.5.2 of the original standard) This article is compiled based on Article 5.1.1, Article 5.1.2 and Article 5.3.2 of YD37--81.
The installation of floor-standing racks should be particularly firm and the machine surface should be flush. Therefore, special emphasis should be placed on the reinforcement parts, especially the overhead equipment, which needs to have stronger stability. After the equipment is unpacked, various parts on the rack should be checked and recorded, and the parts that fall off and are damaged should be reset or replaced in time to ensure the integrity of the rack. 7.1.3 (Reserved provisions of Articles 7.5.1 to 7.5.3 of the original standard) This article is compiled based on Articles 6.1.1, 6.1.2, 6.1.3, 6.2.2, 6.2.4 and 6.2, 5 of YD3781. The machine should be installed firmly and the connections between the machines should be firm to form a whole. In addition, after the machine is installed, the machine surface is almost flat and neat, which can achieve the effect of beautiful machine. Various indicator light covers should be installed according to the specified color to provide convenience for maintenance personnel. 7.2 Allowable Deviation Items
7.2.1 (Revised Article of Article 7.5.4 of the original standard) This article is compiled based on Article 5.1.2 and Article 5.3.1 of YDJ37-81 and Article 5.1.2 and Article 5.1.3 of YDJ41-6. The allowable deviation values ​​listed in this article are the indicators specified in the construction specifications of YDJ37-81 and YDJ41-86.
8 Cable Laying and Bundling Engineering
8.1 Basic Items
8.1.1 (Revised Article of Article 11.4.1 to Article 11.4.5 of the original standard) This article is compiled based on Article 7.1.1, Article 7.1.2, Article 7.1.3 and Article 7.1.4 of YDJ37-81.
Cable bundling is a process requirement. The cross section and position of the circuit routing should be paid special attention when laying cables, because the cross section of the cable will change due to the change of the cable route. If the cable position is incorrect, it will cause the cable to be laid unsmoothly, affecting the neatness and appearance. In addition, the turns of the relay should be smooth and the curvature radius should be greater than 60mm. If it is less than 60mⅡ, it is easy to damage the cable core wire, especially the large-logarithm cable.