JB/T 5054.1-2000 General principles for product drawing design documents
Some standard content:
ICS01.110
J04
JB
Machinery Industry Standard of the People's Republic of China
JB/T5054.1~5054.6-2000
Product drawings and design documents | |tt | 2000 "General Provisions for Product Drawings and Design Documents" and other three machinery industry standards modification notices were approved by the China Machinery Industry Federation with the China Machinery Lianbiao [2001] No. 165 document, and JB/T5054.1 will be implemented on July 1, 2001. -2000 "General Principles of Product Drawings and Design Documents" 1) Supplement
Supplementary entries after 3.2.7, 3.2.8: \3.2.8 Continuous improvement continual improvement is to enhance the satisfaction of express, usually implicit Cyclic activities that must frequently fulfill needs or expectations. \2) Change to new provisions
Article 3.4.7 is changed to new provisions:
“3.4.7 Product Development Project Monthly Suggestions 45productdevelopitemsuggestionbook The product development project proposal is based on feasibility analysis, evaluation and The results of the pilot test shall be used to propose a reasonable product plan, which shall be approved by the enterprise leadership as the basis for product development. "
b3.4.35 shall be replaced by a new article
\3.4.35 Design and Development Review. report designanddevelopmentappraisereport The design and development review report is at the appropriate stage and at the end of the product design and development process, in order to evaluate the ability of the design and development results to meet the requirements, identify any problems and propose necessary measures, and conduct a systematic review of the design and development. Documentation of review results. JB/T5054.3-2000 "Product Drawings and Design Document Format" "]Supplement
In appendix A, add after A1 "The location of each area of ??the A2 title bar should comply with the provisions of GB/T10609.1, and its content when necessary Scalable\. 2) Change
3.3.2 "The detail column should be filled in from top to bottom according to the regulations of each cell" to "The detail column should be filled in from top to bottom according to the regulations of each cell" JB/T5054.5- 2000 "Integrity of Product Drawings and Design Documents" 1) Remove
Delete "3 definition".
2) Change the
a table! In the header of the table, "Non-contract environment" is changed to "Self-developed" and "Contract environment" is changed to "Special contract." b. 7 "New product development project proposal" in Table 1 is changed to "Product development project proposal\". C. "Design review report" in Table 1 is changed to "Design and development review report". d. In the note of Table 1, "One is the leading product or basic product" is changed to "One is mass production product or basic product" Products: "The second is modified products or advanced production products" is changed to: "The second is small batch production products or modified products". ..5.5 a) "The necessity of new product development." is changed to "The necessity of product development." f. "New product development project proposal" in 5.7 was changed to "product development project proposal\: b) "new product development conclusiveness." in 5.7 was changed to "product development conclusiveness.\
. .5.10 d) "Proposal for new product development project." is changed to "Proposal for product development project."; k) "Performance of new product." in 5.10 is changed to "Performance of product." in 5.10 n) "Design and test new products." is changed to "Design and test new products." g) "Standardize new products..." in h.5.32.1 is changed to "Standardize products... .\. .All “Design Review” in Appendix A is changed to “Design and Development Review.\. J. The content of the feasibility analysis review in Table A1 of Appendix A丨"New product development conditions" is changed to "Product development conditions\JB/T5054.1-2000
Foreword
This standard is based on new products To meet the needs of development design and computer-aided design (CAD), refer to the provisions of GB/T17825.1--1999 "General Principles of CAD File Management" and JB/T5054.1-1999 "Terms of Product Drawings and Design Documents" (formerly ZB /TJ01035.1-90) has been modified and adjusted
1. The standard name, due to the addition of content, the chapter has been adjusted, and its name has been changed from "Product Drawings and Design Documents Terminology" to "Product Drawings and Design". Document General
2. The "terminology" of the original standard is unified and listed in Chapter 3 "Definitions\", and the definitions of CAD drawings, CAD files and relevant documents in the decision-making stage are added, as well as the English names of all terms. 3. Standard content, Chapter 4 "CAD File Structure, Classification and Management", Chapter 5 "Rules for Preparation of Drawings and Documents" and Chapter 6 "Signature Rules" have been added.
This standard replaces JB/T5054.11999 from the date of implementation. This standard is proposed and managed by the National Technical Product Document Standardization Technical Committee. This standard was drafted by: China Machinery Industry Standardization Technology Association, Mechanical Science Research Institute, Shenyang Mining Machinery Factory, etc. The main drafters of this standard: Yang Dongbai, Wang Fuzhong, Meng Xianpei, Xu Lintong, Ji Yaqi, Zhou Jingtan. 1Scope
Machinery Industry Standard of the People's Republic of ChinaWww.bzxZ.net
Product drawings and design documents
General principles
Drawing and design document ofproductGeneral principles
JB/T 5054.1- 2000 | , preparation rules and signing rules, etc. This standard applies to the design management of product drawings and documents in the mechanical industry. 2 Referenced standards
The provisions contained in the following standards constitute provisions of this standard through reference in this standard. At the time of publication, the editions indicated were valid. All standards are subject to revision and parties using this standard should explore the possibility of using the latest version of the standard listed below. GB/T 1.31997
GB/T17678.1-—1999
JB/T 5054.22000
JB/T5054.3—2000
JB/T5054.4—2000
JB/T 5054.52000
JB/T5054.6—2000
JB/T 5054.7—1991
3 Definitions
This standard adopts the following definitions.
3.1 Products and their components
3.1.1 product
Standardization Work Guidelines Unit--Unit: Standard Drafting and Presentation Rules Part 3: Product Standard Abbreviation Regulations| |tt||CAD electronic file CD storage archiving and file management Basic requirements for product drawings and design files Product drawings and design file formats
Product drawings and design file numbering principles
Product drawings and design files
Integrity
Product drawings and design documents
Change methods
Standardization review of product drawings and design documents Products are products provided by the manufacturer to users or the market in the form of commodities. Finished product. 3.1.2 Complete set of equipment [complete set of equipment, unit] complete set of equipment [installation, unit] complete set of equipment is the sum of two or more products that are generally not connected in the assembly process in production enterprises, but are used to complete interrelated functions.
National Machinery Industry Bureau approved 2000-03-30
Implemented on 2000-10-01
3.1.3 parts part, detail
JB/T5054.12000| |tt||A part is a single finished product that does not require assembly. 3.1.4 Component subassembly
A component is a finished product composed of several components (parts, subassemblies) in a detachable or non-detachable form. Sub-components can be divided into level 1 sub-components and level-2 sub-components according to their subordination relationships... 3.1.5 Special-parts (basic parts) Special-parts are parts dedicated to this product. 3.1.6 module module
A module is a unit with relatively independent functions and common interfaces. 3.1.7 Borrowing parts graftingpart
Borrowing parts are components of existing products that are used in product drawings with serial numbers. 3.1.8 General parts general part
General parts are interchangeable parts in products of different types or the same type and different specifications. 3.1.9 Standard parts standardparts
Standard parts are parts that have been optimized, simplified, unified, and given standard codes. 3.1.10 Purchase-incomponent Purchase-incomponent refers to the company's products and its components purchased from other companies. 3.1.11 Accessories accessories
Accessories are special tools and testing instruments necessary for users to install, adjust and use products, or are necessary for the product to complete multiple functions (purposes), but cannot be assembled on the product at the same time. Part. 3.1.12 Consumable parts wearpart
Consumable parts are parts that are easily damaged during normal use (operation) of the product and must be replaced within a specified period. 3.1.13 Spare parts spareparts
Spare parts are spare parts and other parts provided to users to ensure the use and maintenance of the product. 3.2 Product design and trial production process
3.2.1 Development decision-making development policy Development decision-making is the work carried out to investigate and determine the projects and goals of product design and development. 3.2.2 Preliminary design preliminary design is the work carried out to research and determine the best design of the product. 3.2.3 Technical design technical design Technical design is the work of designing and calculating the structure and parameters of the product and its components, and drawing the overall product drawing and main component drawings. 3.2.4 Working drawing design Working drawing design is the work of drawing all product working drawings and preparing necessary design documents based on technical design. 3.2.5 Prototype (sample) trial production prototype (sample) trial production Prototype (sample) trial production is a trial production work carried out to verify the structure and performance of new products. 3.2.6 Small batch trial production trialproductioninsmallnumbersSmall batch trial production is a trial production work carried out to verify the formal production process, tooling, and the modified drawings and design documents after prototype (sample) trial production.
3.2.7 Formal production normalproductionJB/T5054.1-2000
Formal production is produced in accordance with the trial production and final modified drawings, design documents and determined process requirements. 3.2.8 Continuous improvement Continuous improvement is a cyclic activity that enhances the ability to meet stated, usually implicit, or must-fulfill needs or expectations. 3.3 Product drawings\
3.3.1 Classification by represented objects
3.3.1.1 Parts drawing detaildrawing
Parts drawings are drawings used for manufacturing and inspecting parts. Necessary data and technical requirements should be included. 3.3.1.2 Assembly drawing assembly drawing is a drawing that expresses the parts and parts, parts and parts, or the connections between parts in products and components, including the data and technical requirements necessary for assembly (processing and inspection). Product assembly drawings are also called general assembly Figure. When the product assembly drawing contains the content required by the general drawing, it can be used as a general drawing. 3.3.1.3 General drawing
The general drawing expresses the structural overview, mutual relationships and basic performance of the product and its components. Drawing. When the appearance, installation and connection dimensions of the product and its components are noted in the general drawing, it can be used as an outline drawing or installation drawing. 3.3.1.4 Overall drawing
Product outline drawings of installation and connection dimensions. If necessary, the distance between protruding parts and the maximum limit position dimensions of operating parts and moving parts should be noted. The installation drawing is a diagram of the product and its components. The gallery diagram represents the installation drawing at the place of use, and includes the necessary data, parts, materials and instructions for installation. 3.3.1.6 Diagram Diagram
Diagram uses prescribed graphic symbols, codes and tubes. A general term for schematic diagrams drawn by drawing methods, such as schematic diagrams, system diagrams, block diagrams, wiring diagrams, etc.
a) Schematic diagram, elementary diagram expresses the working procedures, functions and components of the product. A simple diagram of the principles of structure, action, etc. Such as electrical schematic diagram, hydraulic schematic diagram, etc. || tt | A simplified diagram of. c) Block diagram squarediagram
A block diagram is generally a simplified form of annotated boxes that shows the mutual relationships and layout of components in a product or complete set of equipment.
1connectiondiagram
d) Wiring diagram
1) Drawings that draw views and compile technical requirements are called drawings. JB/T5054.1-2000
The wiring diagram is a working drawing showing the installation, connection, and wiring of various electrical components in the entire system or part of the system based on the electrical schematic diagram. Each connection part (terminal) is marked separately. 3.3.1.7 Tabular drawing
Tabular drawing is a working drawing that uses a table to represent two or more similar parts, components or products with the same shape, and includes necessary data and technical requirements.
3.3.1.8 Packaging drawing packagedrawing
Packaging drawing is a transportation packaging drawing designed and drawn in accordance with relevant regulations for safe storage and transportation of products. 3.3.2 Classification according to completion method and usage characteristics 3.3.2.1 Original drawing (draft) original drawing The original drawing (draft) is a pattern (document) used for making base drawings or for copying. Note: The original drawing (draft) can be used as the base drawing (draft), but it must be confirmed that the signature of the person responsible for the drawing (document) is correct. 3.3.2.2 Base drawing (draft) sourcedrawing base drawing () is a pattern (document) used to make a copy of the drawing (draft) after completing the prescribed signing procedures. 3.3.2.3 Sub-base drawing (draft) sourcedrawingcopy The sub-base drawing (draft) is the same as the base drawing (draft). A copy of the base map (draft) that is exactly the same as the drawing (draft). 3.3.2.4 Duplicate drawings (drafts) Duplicate drawings (drafts) are drawings (documents) produced using a method that ensures that they are completely consistent with the base drawings (drafts) or sub-base drawings (drafts). Note: Use microcopy drawings (drafts) ( The microcopy drawings (drafts) produced by the original drawings (drafts) are also photocopied drawings (drafts). 3.3.2.5 CAD drawing CAD drawing
CAD drawing is the drawing produced in the CAD process. It refers to the use of computers to draw the geometric characteristics, shape, position and size of things with points, lines, symbols and numbers, including various types of drawings related to product or engineering design. :3.3.2.6 CAD files CADdocument
CAD files are all files generated by computers during the CAD process, and refer to all CAD drawings and design files necessary to realize the product.
3.3.3 Classification by design process
3.3.3.1 Design drawing designdrawing Design drawing is the drawing drawn during preliminary design and technical design. 3.3.3.2 Working pattern The working pattern is drawn during the design of the working drawing and includes drawings of structural dimensions, data and technical requirements necessary for the manufacture and inspection of the product and its components. Prototype (sample) trial production drawings, small batch trial production drawings and formal production drawings are all working drawings. 3.4 Design-related documents
3.4.1 Market forecast report marketpredictionThe market forecast report is the collection and analysis of information such as product demand, market dynamics, economic benefits, and technological development by corporate marketing and technology departments to provide the enterprise with Determine the basis for product structure, new product development and marketing strategies. 3.4.2 Technical investigation report technical investigation report The technical investigation report is the research and analysis of the product level development trend, product quality information, economic effects, etc. by the enterprise's technical department, and proposes new product ideas, standards and regulations that should be implemented, and serves as the basis for new product development decisions. . 3.4.3 The pilot test program fisttestprogramJB/T5054.1—2000
The pilot test program is a test project, requirement, etc. proposed for the performance of new technologies, new principles, new structures, new materials, and new processes to be adopted. document.
3.4.4 Pilot test report fisttestreport The pilot test report is a document prepared according to the requirements of the pilot test program to conduct test verification and obtain data and results. 3.4.5 Feasibility analysis report feasibility analysis report The feasibility analysis report is based on the market forecast and technical research content of the enterprise, through the analysis of the product's main technical performance, life cycle, enterprise production conditions, production capacity, production cost and expected social economy and benefits, for Provide basis for product development decisions. 3.4.6 Feasibility analysis review report feasibility analysisappraisereport The feasibility analysis review report is a document prepared as a result of the evaluation and review of the feasibility analysis report. 3.4.7 Product development project proposal product development project proposal is a document that proposes a reasonable plan for a new product based on the results of feasibility analysis, review and pilot testing: after approval by the corporate legal person, it serves as the basis for new product development. 3.4.8 Technical quotation technical quotation Technical quotation is a document prepared by the design unit for the subject matter of the user's bid or the product's pre-sales service quotation. It is one of the basis for forming the technical agreement.
3.4.9 Technical Agreement technical agreement The technical agreement is a document prepared by both the supply and demand parties regarding the development product level, structural performance, applicable regulations and other requirements. It is an attachment to the contract and is one of the basis for product acceptance. 3.4.10 Technical (design) assignment technical (design) assignment The technical (design) assignment is a document in which the design unit puts forward recommendations on the planned assignment that reflect the reasonable solution for the product. After approval by the competent department, it will be used as the basis for product technical design. 3.4.11 Technical recommendation Technical recommendation is a document that the design unit proposes to the purchaser regarding the technical agreement that embodies the reasonable solution for the product. With the consent of the purchaser, it will be used as the basis for product technical design. 3.4.12 Research and Development Program The research and development program research and test program is a document of research and test projects, requirements, etc. proposed by preliminary design and technical design for certain new technologies, principles, structures, materials, and to achieve certain performance. 3.4.13 Research and development report research and development report The research and development report is a document prepared on the basis of the data and conclusions obtained from the test verification according to the requirements of the research and test outline. 3.4.14 Technical design description technical design description The technical design description is an explanatory document on the product structure, working principle, technical performance and other aspects determined in the technical design. 3.4.15 Calculation sheet Calculation sheet is a document of theoretical calculations on the performance, main structure, system, safety, strength, etc. of the product. 3.4.16 Technical and economic analysis report technical and economic analysis The technical and economic analysis report is a document that uses methods such as system engineering, feasibility engineering and value engineering to demonstrate the technical and economic rationality of the product and its components.
6
3.4.17 File directory documentlist
JB/T5054.1-2000
The file directory is the design file list of the product or component. 3.4.18 Drawinglist
The drawing list is a list of a complete set of working drawings for a product or component. 3.4.19 detailed list detailed list
The detailed list is a list showing the components of the product or component. 3.4.20 Summary list itemized list
The summary list is classified based on the detailed list or detail column. Comprehensive and compiled table. Such as standard parts summary table, purchased parts summary table, series product module summary table, etc. 3.4.21 Product technical conditions product technical specifications5 Product technical conditions are documents that express the technical requirements for manufacturing, testing and inspection of product components that are not suitable for expression in working drawings.
3.4.22 Product standards productstandard Product standards are standards established to ensure the applicability of products and set some or all of the requirements that products must meet. The content is in accordance with the provisions of GB/T1.3.
3.4.23 Operation instructions operation instructions are documents for users to understand the product, correctly lift, install, adjust, use and maintain the product 3.4.24 Certificate of conformity (certificate of conformity) certificate of conformity (certificate of conformity) ) is a document proving that the product is qualified after inspection. 3.4.25 Quality certificate certificate of quality Quality certificate is a document prepared by the manufacturing unit to provide users with various test data, original certificates, etc. regarding product performance, safety and reliability. | | tt | 3.4.27 Standardization review report examination report of standardization Standardization review report is a document prepared based on the review results of the implementation and implementation of comprehensive requirements for standardization during the design and trial production process of new products.
3.4.28 The Appraisal Program of Trial Production Appraisal Program of Trial Production Appraisal Program is a document prepared for the design documents, special instruments, test sites, test procedures, methods and requirements required for inspection and testing items when identifying products. . 3.4.29 Summary of trial production Summary of trial production Summary of trial production is a document prepared by analyzing and summarizing the problems, solutions and test verifications that arise and exist in the design and process during trial production during prototype (sample) trial production and small batch trial production. 3.4.30 Type test report type-testreport The type test report is a document prepared after comprehensive inspection of various quality indicators of the prototype (sample) according to the requirements of product standards (or product technical conditions).
3.4.31 trial operation report7 Product development project proposal product development project proposal is a document that proposes a reasonable plan for a new product based on the results of feasibility analysis, review and pilot testing: after approval by the corporate legal person, it serves as the basis for new product development. 3.4.8 Technical quotation technical quotation Technical quotation is a document prepared by the design unit for the subject matter of the user's bid or the product pre-sales service quotation. It is one of the basis for forming the technical agreement.
3.4.9 Technical Agreement technical agreement The technical agreement is a document prepared by both the supply and demand parties regarding the development product level, structural performance, applicable regulations and other requirements. It is an attachment to the contract and is one of the basis for product acceptance. 3.4.10 Technical (design) assignment technical (design) assignment The technical (design) assignment is a document in which the design unit puts forward recommendations on the planned assignment that reflect the reasonable solution for the product. After approval by the competent department, it will be used as the basis for product technical design. 3.4.11 Technical recommendation Technical recommendation is a document that the design unit proposes to the purchaser regarding the technical agreement that embodies the reasonable solution for the product. With the consent of the purchaser, it will be used as the basis for product technical design. 3.4.12 Research and development program research and development program The research and development program is a document of research and test projects, requirements, etc. proposed by preliminary design and technical design for certain new technologies, principles, structures, materials, and to achieve certain performance. 3.4.13 Research and development report research and development report The research and development report is a document prepared on the basis of the data and conclusions obtained from the test verification according to the requirements of the research and test outline. 3.4.14 Technical design description technical design description The technical design description is an explanatory document on the product structure, working principle, technical performance and other aspects determined in the technical design. 3.4.15 Calculation sheet Calculation sheet is a document of theoretical calculations on the performance, main structure, system, safety, strength, etc. of the product. 3.4.16 Technical and economic analysis report technical and economic analysis The technical and economic analysis report is a document that uses methods such as system engineering, feasibility engineering and value engineering to demonstrate the technical and economic rationality of the product and its components.
6
3.4.17 File directory documentlist
JB/T5054.1-2000
The file directory is the design file list of the product or component. 3.4.18 Drawinglist
The drawing list is a list of a complete set of working drawings for a product or component. 3.4.19 detailed list detailed list
The detailed list is a list showing the components of the product or component. 3.4.20 Summary list itemized list
The summary list is classified based on the detailed list or detail column. Comprehensive and compiled table. Such as standard parts summary table, purchased parts summary table, series product module summary table, etc. 3.4.21 Product technical conditions product technical specifications5 Product technical conditions are documents that express the technical requirements for manufacturing, testing and inspection of product components that are not suitable for expression in working drawings.
3.4.22 Product standards productstandard Product standards are standards established to ensure the applicability of products and set some or all of the requirements that products must meet. The content is in accordance with the provisions of GB/T1.3.
3.4.23 Operation instructions operation instructions are documents for users to understand the product, correctly lift, install, adjust, use and maintain the product 3.4.24 Certificate of conformity (certificate of conformity) certificate of conformity (certificate of conformity) ) is a document proving that the product is qualified after inspection. 3.4.25 Quality certificate certificate of quality Quality certificate is a document prepared by the manufacturing unit to provide users with various test data, original certificates, etc. regarding product performance, safety and reliability. | | tt | 3.4.27 Standardization review report examination report of standardization Standardization review report is a document prepared based on the review results of the implementation and implementation of comprehensive requirements for standardization during the design and trial production process of new products.
3.4.28 The Appraisal Program of Trial Production Appraisal Program of Trial Production Appraisal Program is a document prepared for the design documents, special instruments, test sites, test procedures, methods and requirements required for inspection and testing items when identifying products. . 3.4.29 Summary of trial production Summary of trial production Summary of trial production is a document prepared by analyzing and summarizing the problems, solutions and test verifications that arise and exist in the design and process during trial production during prototype (sample) trial production and small batch trial production. 3.4.30 Type test report type-testreport The type test report is a document prepared after comprehensive inspection of various quality indicators of the prototype (sample) according to the requirements of product standards (or product technical conditions).
3.4.31 trial operation report7 Product development project proposal product development project proposal is a document that proposes a reasonable plan for a new product based on the results of feasibility analysis, review and pilot testing: after approval by the corporate legal person, it serves as the basis for new product development. 3.4.8 Technical quotation technical quotation Technical quotation is a document prepared by the design unit for the subject matter of the user's bid or the product pre-sales service quotation. It is one of the basis for forming the technical agreement.
3.4.9 Technical Agreement technical agreement The technical agreement is a document prepared by both the supply and demand parties regarding the development product level, structural performance, applicable regulations and other requirements. It is an attachment to the contract and is one of the basis for product acceptance. 3.4.10 Technical (design) assignment technical (design) assignment The technical (design) assignment is a document in which the design unit puts forward recommendations on the planned assignment that reflect the reasonable solution for the product. After approval by the competent department, it will be used as the basis for product technical design. 3.4.11 Technical recommendation Technical recommendation is a document that the design unit proposes to the purchaser regarding the technical agreement that embodies the reasonable solution for the product. With the consent of the purchaser, it will be used as the basis for product technical design. 3.4.12 Research and Development Program The research and development program research and test program is a document of research and test projects, requirements, etc. proposed by preliminary design and technical design for certain new technologies, principles, structures, materials, and to achieve certain performance. 3.4.13 Research and development report research and development report The research and development report is a document prepared on the basis of the data and conclusions obtained from the test verification according to the requirements of the research and test outline. 3.4.14 Technical design description technical design description The technical design description is an explanatory document on the product structure, working principle, technical performance and other aspects determined in the technical design. 3.4.15 Calculation sheet Calculation sheet is a document of theoretical calculations on the performance, main structure, system, safety, strength, etc. of the product. 3.4.16 Technical and economic analysis report technical and economic analysis The technical and economic analysis report is a document that uses methods such as system engineering, feasibility engineering and value engineering to demonstrate the technical and economic rationality of the product and its components.
6
3.4.17 File directory documentlist
JB/T5054.1-2000
The file directory is the design file list of the product or component. 3.4.18 Drawinglist
The drawing list is a list of a complete set of working drawings for a product or component. 3.4.19 detailed list detailed list
The detailed list is a list showing the components of the product or component. 3.4.20 Summary list itemized list
The summary list is classified based on the detailed list or detail column. Comprehensive and compiled table. Such as standard parts summary table, purchased parts summary table, series product module summary table, etc. 3.4.21 Product technical conditions product technical specifications5 Product technical conditions are documents that express the technical requirements for manufacturing, testing and inspection of product components that are not suitable for expression in working drawings.
3.4.22 Product standards productstandard Product standards are standards established to ensure the applicability of products and set some or all of the requirements that products must meet. The content is in accordance with the provisions of GB/T1.3.
3.4.23 Operation instructions operation instructions are documents for users to understand the product, correctly lift, install, adjust, use and maintain the product 3.4.24 Certificate of conformity (certificate of conformity) certificate of conformity (certificate of conformity) ) is a document proving that the product is qualified after inspection. 3.4.25 Quality certificate certificate of quality Quality certificate is a document prepared by the manufacturing unit to provide users with various test data, original certificates, etc. regarding product performance, safety and reliability. | | tt | 3.4.27 Standardization review report examination report of standardization Standardization review report is a document prepared based on the review results of the implementation and implementation of comprehensive requirements for standardization during the design and trial production process of new products.
3.4.28 The Appraisal Program of Trial Production The Appraisal Program of Trial Production The trial production appraisal program is a document prepared for the design documents, special instruments, test sites, test procedures, methods and requirements required for inspection and testing items when identifying products. . 3.4.29 Summary of trial production Summary of trial production Summary of trial production is a document prepared by analyzing and summarizing the problems, solutions and test verifications that arise and exist in the design and process during trial production during prototype (sample) trial production and small batch trial production. 3.4.30 Type test report type-testreport A type test report is a document prepared after comprehensive inspection of various quality indicators of a prototype (sample) according to the requirements of product standards (or product technical conditions).
3.4.31 trial operation report19 detailed list detailed list | And the prepared form. Such as standard parts summary table, purchased parts summary table, series product module summary table, etc. 3.4.21 Product technical conditions product technical specifications5 Product technical conditions are documents that express the technical requirements for manufacturing, testing and inspection of product components that are not suitable for expression in working drawings.
3.4.22 Product standards productstandard Product standards are standards established to ensure the applicability of products and set some or all of the requirements that products must meet. The content is in accordance with the provisions of GB/T1.3.
3.4.23 Operation instructions operation instructions are documents for users to understand the product, correctly lift, install, adjust, use and maintain the product 3.4.24 Certificate of conformity (certificate of conformity) certificate of conformity (certificate of conformity) ) is a document proving that the product is qualified after inspection. 3.4.25 Quality certificate certificate of quality Quality certificate is a document prepared by the manufacturing unit to provide users with various test data, original certificates, etc. regarding product performance, safety and reliability. | | tt | 3.4.27 Standardization review report examination report of standardization Standardization review report is a document prepared based on the review results of the implementation and implementation of comprehensive requirements for standardization during the design and trial production process of new products.
3.4.28 The Appraisal Program of Trial Production The Appraisal Program of Trial Production The trial production appraisal program is a document prepared for the design documents, special instruments, test sites, test procedures, methods and requirements required for inspection and testing items when identifying products. . 3.4.29 Summary of trial production Summary of trial production Summary of trial production is a document prepared by analyzing and summarizing the problems, solutions and test verifications that arise and exist in the design and process during trial production during prototype (sample) trial production and small batch trial production. 3.4.30 Type test report type-testreport A type test report is a document prepared after comprehensive inspection of various quality indicators of a prototype (sample) according to the requirements of product standards (or product technical conditions).
3.4.31 trial operation report19 detailed list detailed list | And the prepared form. Such as standard parts summary table, purchased parts summary table, series product module summary table, etc. 3.4.21 Product technical conditions product technical specifications5 Product technical conditions are documents that express the technical requirements for manufacturing, testing and inspection of product components that are not suitable for expression in working drawings.
3.4.22 Product standards productstandard Product standards are standards established to ensure the applicability of products and set some or all of the requirements that products must meet. The content is in accordance with the provisions of GB/T1.3.
3.4.23 Operation instructions operation instructions are documents for users to understand the product, correctly lift, install, adjust, use and maintain the product 3.4.24 Certificate of conformity (certificate of conformity) certificate of conformity (certificate of conformity) ) is a document proving that the product is qualified after inspection. 3.4.25 Quality certificate certificate of quality Quality certificate is a document prepared by the manufacturing unit to provide users with various test data, original certificates, etc. regarding product performance, safety and reliability. | | tt | 3.4.27 Standardization review report examination report of standardization Standardization review report is a document prepared based on the review results of the implementation and implementation of comprehensive requirements for standardization during the design and trial production process of new products.
3.4.28 The Appraisal Program of Trial Production The Appraisal Program of Trial Production The trial production appraisal program is a document prepared for the design documents, special instruments, test sites, test procedures, methods and requirements required for inspection and testing items when identifying products. . 3.4.29 Summary of trial production Summary of trial production Summary of trial production is a document prepared by analyzing and summarizing the problems, solutions and test verifications that arise and exist in the design and process during trial production during prototype (sample) trial production and small batch trial production. 3.4.30 Type test report type-testreport The type test report is a document prepared after comprehensive inspection of various quality indicators of the prototype (sample) according to the requirements of product standards (or product technical conditions).
3.4.31 trial operation report
Tip: This standard content only shows part of the intercepted content of the complete standard. If you need the complete standard, please go to the top to download the complete standard document for free.