This standard specifies the annual working month, annual construction month and monthly man-day quotas for seismic exploration work carried out by seismic exploration teams in areas with different climate, landform and environmental conditions. This standard is applicable to all types of seismic exploration teams. SY 5491-1992 Labor quotas for construction man-days for seismic explorationSY5491-1992 Standard download decompression password: www.bzxz.net
Some standard content:
Petroleum and Natural Gas Industry Standard of the People's Republic of China SY5491-92 Labor quota for seismic exploration construction work day 1992-11-03 Issued Ministry of Energy of the People's Republic of China 1993-04-01 Implementation 1 Subject content and applicable scope Petroleum and Natural Gas Industry Standard of the People's Republic of China Labor quota for seismic exploration construction work day SY 5491-92 This standard specifies the quotas for annual working months, annual working months and monthly working days for seismic exploration teams to carry out seismic exploration work in areas with different climate, landform and environmental conditions. This standard applies to various seismic exploration teams. 2 Terminology 2.1 Annual working month The number of working months specified in a year. Including the number of months of the construction period and the preparation and end time of the construction period. 2.2 Annual construction months Number of quota construction months for the construction period specified in a year. 2.3 Construction period preparation and end time Time required for production organization, technology, testing, material preparation before the construction period and data acceptance, equipment arrangement, etc. after the construction period within a year. 2.4 Construction man-days Construction calendar days on which the ground exploration team obtains production records. 2.5 Quota man-days Construction man-days specified in this standard. 2.6 Conversion man-days Man-days converted from the construction site working hours of construction man-days according to the specified number of hours. 2.7 Maintenance day Calendar days for maintenance of equipment and special tools during the construction period as specified in the technical regulations and equipment management. 2.8 Organizational suspension day Calendar days on which work is suspended for activities such as political ideology, production technology, and safety education for employees. 2.9 Natural downtime days The calendar of downtime days due to natural reasons such as rain, snow, wind, etc. 2.10 Public holidays The rest days stipulated during the construction period, including statutory holidays and public holidays. 2.11 Site working hours The length of time between construction, entering and leaving the construction site, measured in hours. The monthly and monthly working day utilization quotas for the construction of the seismic exploration team in 2011 are shown in Table 1. The application calculation formula of the monthly and monthly working day utilization quotas for the construction of the seismic exploration team in 2011 is shown in Appendix A (reference). Approved by the Ministry of Energy of the People's Republic of China on November 3, 1992 and implemented on April 1, 1993 The length of the seismic exploration team's quota working day 4. 1 The length of the seismic exploration team's quota working day is 9h. SY5491-92 4.2 The ground exploration team uses 9 hours of ground exploration equipment site work as one converted working day. Table 1 The use of monthly construction month and monthly working day quotas of the ground exploration team Geographical area Yearly working months Yearly construction months Yearly quasi-finished months of construction period Organized suspension Natural suspension Working months Yearly construction months Yearly quasi-finished months of construction period Organized suspension Natural suspension Fulinguole League General area 33° north latitude 33°~~42° South-central Liaoning ProvincewwW.bzxz.Net General Area Qaidam area South of 33° north latitude Car-mounted drilling construction area Man-lifted drilling area Tuyiha area General area All-year construction area A1 Monthly and annual labor quota of seismic exploration team SY5491—92 Appendix A Calculation of monthly and annual labor quotas (reference) The monthly and annual labor quotas of seismic exploration teams must be calculated by multiplying the standard monthly and annual construction days by the team's daily labor quota of the relevant labor quota standards. Team monthly quota Q: Q,-Q - S. Where: Q,—Team monthly quota, gun or kilometer; Q--…Team daily quota, gun or kilometer, S. Monthly quota construction days. A1.2Team annual quota Q: Q=Q, - S. . S. Where, Q—Team annual quota, gun or kilometer, Annual quota construction months. Additional remarks: This standard was proposed by China National Petroleum Corporation. This standard is under the jurisdiction of the Technical Committee for Standardization of Labor Quotas in the Petroleum Industry. This standard was drafted by the Petroleum Geophysical Exploration Bureau of China National Petroleum Corporation. Sichuan Petroleum Administration Bureau participated. This standard is interpreted by the Technical Committee for Standardization of Labor Quotas in the Petroleum Industry. The main drafters of this standard are Xie Kailin, Tang Fengju and Han Changshou. (A1) Tip: This standard content only shows part of the intercepted content of the complete standard. If you need the complete standard, please go to the top to download the complete standard document for free.