title>SY 4028-1993 Petroleum construction project quality inspection and assessment standard equipment installation project - SY 4028-1993 - Chinese standardNet - bzxz.net
Home > SY > SY 4028-1993 Petroleum construction project quality inspection and assessment standard equipment installation project
SY 4028-1993 Petroleum construction project quality inspection and assessment standard equipment installation project
Basic Information
Standard ID:
SY 4028-1993
Standard Name: Petroleum construction project quality inspection and assessment standard equipment installation project
This standard applies to the inspection and evaluation of the quality of equipment installation engineering in petroleum construction projects. SY 4028-1993 Inspection and evaluation standard for quality of petroleum construction projects Equipment installation engineering SY4028-1993 Standard download decompression password: www.bzxz.net
Some standard content:
Standard for Quality Inspection and Evaluation of Petroleum Construction Engineeringthe work for Plant InstallationSY4028--93 Editor: China National Petroleum Corporation Infrastructure Engineering BureauApproval department: China National Petroleum CorporationImplementation date: March 1, 1994 Petroleum Industry Press 1993·Beijing Blower installation project· Piston gas compressor installation project Oil pump installation project Pump installation project Water injection pump installation project Long-distance pipeline oil pump group installation project Steel cylindrical container installation project Original turbidity electric dehydration container installation project Atmospheric pressure container installation project Equipment insulation project Integral boiler and accessories installation project Heating furnace installation Engineering Oilfield special wet steam generator installation project·Appendix A Appendix B Appendix ℃ Appendix D Construction and acceptance specifications for use with this standard Equipment installation project quality assurance materials Inspection instrument list· Explanation of terms used in this standard Additional instructions Document of China National Petroleum Corporation (93) Zhongyoujizi No. 598 Notice on the approval and release of 27 oil and gas industry standards including "Regulations for the Preparation of Oil Surface Engineering Design Documents" To all relevant units and relevant petroleum professional standardization technical committees: The draft of 27 standards including "Regulations for the Preparation of Oil Surface Engineering Design Documents" has been reviewed and approved and is now approved as oil and gas industry standards. The numbers and names of the standards are as follows: SY 0009—93 SY 0055--93 SY 0072---93 0073—93 SY 0074--93 SY/T 0076—93 SY/T 0077--93 SY/T 0523---93 SY 4024—93 Specification for the preparation of documents for design of petroleum surface engineering (replacing SYJ 9—83) Specification for the measurement of long-distance oil and gas pipelines (replacing SYJ 55—83) Standard for the test method of high temperature cathodic disbonding of pipeline corrosion layerStandard for the test method of pipeline anticorrosion layer patch materialStandard for the test method of insulation and sealing of pipeline anticorrosion layer patchWho Design specification for natural gas dehydration Design specification for natural gas condensate recovery Oilfield water treatment filter Standard for quality inspection and assessment of petroleum construction projectsGeneral purchase (replaces SYJn 4024—88) SY4025—93 SV 4026--93 Sy 402793 SY 402893 14SY4029-93 15 SY 4030.1—93 SY 4030-2---93 SY 4031--93 5Y 4033---93 SY 4034--93 5r 4035--93 21SY4037-93 Standard for quality inspection and assessment of petroleum construction projects Construction projects (replacing SYJn4025-88) Standard for quality inspection and assessment of petroleum construction projects Storage tank projects (replacing SYJn4026-88) Standard for quality inspection and assessment of petroleum construction projects Steel process pipeline installation projects within stations (replacing SYJn4027--88) Standard for quality inspection and assessment of petroleum construction projects Equipment installation projects (replacing SYJn4028-88) Standard for quality inspection and assessment of petroleum construction projects Long-distance pipeline projects (replacing SYJu4029-88) Standard for quality inspection and assessment of petroleum construction projects Electrical engineering (overhead power line projects) (replacing SJn 40$088) Petroleum construction project quality inspection and assessment standard electrical engineering (electrical equipment installation engineering) (Replace SYJn4030-88) Petroleum construction project quality inspection and assessment standard automation instrument installation engineering (Replace SYJ 4031--88) Petroleum construction project quality inspection and assessment standard road engineering (Replace SYJn4033-88) Petroleum construction project quality inspection and assessment standard bridge engineering (Replace SYJn4034-88) Petroleum construction project quality inspection and assessment standard heating, ventilation, water supply and drainage installation engineering (Replace SYJn 4035-88) Petroleum construction project quality inspection and assessment standard refinery 22 SY 4038-93 23SY 4053—93 SYT 4068-93 25SY/T4069--93 26 SY 4070—93 Construction Engineering Replace SYJ4037-—89) Petroleum Construction Engineering Quality Inspection and Assessment Standard Gas Field Construction Engineering (Replace SY4038--92) Petroleum Construction Engineering Quality Inspection and Assessment Standard Oilfield Gathering and Transportation Pipeline Engineering (Replace SY4053--92) Petroleum Construction Engineering Quality Inspection and Assessment Standard Glass Insulation Steel Pipe Manufacturing Petroleum Construction Engineering Quality Inspection and Assessment Standard Oilfield Steel Container Manufacturing Petroleum and Natural Gas Pipeline Crossing Engineering Construction and Acceptance Specification Pipeline Downward Welding Process Specification 27SYT 407193 The above standards shall be implemented from March 1, 1994. China National Petroleum Corporation September 9, 1993 1 General Provisions 1.0.1 The standard is applicable to the inspection and evaluation of equipment engineering quantities of petroleum construction projects. The main parts are divided as follows: 1.0.1.1 Fan installation project: This chapter is applicable to the installation of centrifugal fans, centrifugal blowers, centrifugal compressors, and axial flow fans. 1.0.1.2 Piston gas compressor installation project: This chapter is applicable to the overall installation of various types of vertical and horizontal piston gas compressors used in oil fields. 1.0.3 Pumping unit installation project: This chapter is applicable to various types of oil field pumping units. Installation of single-axis single-axis machine with braid and chain case: 1.0, 1.4 Pump installation project: This chapter applies to the overall installation of various types of centrifugal pumps, axial flow pumps, deep well pumps, gear pumps, screw pumps and reciprocating pumps. 1.0.1.5 Water injection pump installation project. This chapter applies to the installation of centrifugal and plunger water injection pumps with a design pressure of less than 45MPa in oil injection projects. 1.0.1.6 Long-distance pipeline oil pump group installation project. This chapter applies to the overall installation of long-distance pipeline oil pump groups. 1.0.1.7 Steel cylindrical container installation project. This chapter applies to oilfield working pressure not more than 9 .8MPa, the installation of carbon steel, ordinary low-pressure steel cylindrical containers (including high-pressure filter tanks, separators, buffer cylinders, free water removers) with a diameter not exceeding 4m, 1.0.1.8 Crude oil electric dehydration container installation project: This chapter is applicable to the installation of crude oil electric dehydrators made of carbon steel and ordinary low-pressure steel with a design pressure not exceeding 1.0MPa and a design temperature not exceeding 150℃ in oil fields: 1.01.9 Atmospheric pressure container installation project: This chapter is applicable to the installation of atmospheric pressure containers with the following technical conditions 1) Steel welded small circular vertical tanks, horizontal tanks or elliptical horizontal tanks Tanks, whose volume should not exceed 100m3: their designed pressure should not be less than 0.002MPa and should not exceed 1 (2) Water tanks, oil tanks, pickling tanks, electrolytic cells, chutes, funnels, etc. welded with carbon steel, ordinary low alloy steel, stainless acid-resistant steel, their designed pressure should not exceed 0.05MPa and their volume should not exceed 40m3 1.0.1.10 Equipment insulation engineering This chapter applies to the insulation engineering of oilfield equipment installation 1.0.1.11 Integral boiler and accessories installation engineering: This chapter applies to the installation of integral boilers shipped from the oilfield industry and civil use 1.0.1.12 Heating furnace installation project: This chapter is applicable to the installation of heating furnaces with the following technical conditions: (1) Water-jacketed heat suppression furnace with shell design pressure not exceeding 0.5MPa and tube design pressure not exceeding 20MPa: (2) Fire-type heating furnace with shell design pressure not exceeding 0.98MPa and heat load of 2.1~12.6GI/h; (3) Separation, heating, buffering and closing devices with shell design pressure not exceeding 0.9MPa and heat load of 2.1~12.6GJ/h; (4) Horizontal circular tube heating furnace with tube design pressure not exceeding 9.8MPa and heat load not exceeding 12.6GJ/h (only included in whole factory delivery); 1.0.1.13 Oilfield-specific wet steam generator installation project: This chapter is applicable to the installation of oilfield-specific wet steam generator. 1.02 The division of equipment installation engineering sub-items and sub-section (unit) engineering shall comply with the following provisions: Sub-item engineering: Equipment installed as a whole is generally divided by equipment sets. Large equipment installation is generally divided by process. Sub-section engineering: Equipment installation engineering in the same unit engineering together constitutes a sub-section engineering. The installation of each human-type equipment is a sub-section (unit) engineering. The names of sub-items and sub-section (unit) engineering shall comply with the provisions of Table 1, 0.2. 1.03 The quality inspection and assessment of the sub-item engineering of ladder, platform, railing production and installation engineering and painting engineering related to this bid shall comply with the provisions of Chapter 10 and Chapter 14 of SY4026 "Standard for Quality Inspection and Assessment of Petroleum Construction Engineering Tank Engineering". 2 Division of sub-projects and sub-section (unit) projects Sub-section (unit) project name Equipment installation project Machine pump installation project Container installation project Furnace installation project Sub-project name 1.8.2 Fan installation; Gas compressor installation: Pumping unit installation: Pump installation: Injection pump installation: Long pipeline oil pump group installation Steel circular container installation: Crude oil electric ice melter installation: Atmospheric pressure container transfer: Equipment filter integral boiler and accessories installation: Oil-specific wet precipitation generator installation: Heating furnace installation 1.0.4 While implementing this standard, the provisions of SY4024 "General Rules for Quality Inspection and Assessment of Petroleum Construction Projects" should also be observed. 1.0.5 The main quality indicators and quality requirements of this standard are proposed in accordance with the current national and industry standards and construction and acceptance specifications (see Appendix A for details). 1.0.6 The quality assurance data of the equipment installation project of this standard is shown in Appendix B. 1.0.8 The table of inspection instruments for the equipment installation project of this standard is shown in Appendix C. 1.0.8 The explanation of the terms used in this standard is shown in Appendix D: 9www.bzxz.net Fan installation project 2.1 Guarantee items 2.1.1 The fan must have a factory qualification certificate and equipment technical documents. Inspection method: Check the factory qualification certificate and equipment technical documents. 2.1.2 The trial operation of the fan must comply with the design requirements or the provisions of relevant specifications. Inspection method: Check the trial operation records. 2.1.3 The cleaning of the fan must comply with the design requirements or the provisions of relevant specifications. Inspection method: Check the cleaning records. 2.14 The noise reduction and vibration prevention of the fan must comply with the design requirements. Inspection method: Use instrument to test or check the test record. 2.2 Basic items Quality requirements for anchor bolts and their inspection quantity, inspection method, and specified score table 2.2.1 Quality requirements Bolts should be vertical and without tilt The bare rod of the bolt should be free of oil and oxidation scale, and the threaded part should be lightly greased Bolts should not touch the bottom of the hole, and any part of the bolt should be no less than The distance from the hole wall to any part of the bolt should not be less than After the nut is tightened, the exposed thread of the bolt is 2~~~5 turns, and the distance between the nut and the washer, and the washer and the base should be uniform. The contact should be good Inspection quantity The total number of fans in a factory, workshop or station should be randomly selected inspected 20%, but not less than one Inspection method Observation inspection Observation inspection or measurement inspection Observation inspection or wrench inspection 2.2, 1 The quality requirements for the installation of anchor bolts and their inspection quantity, inspection methods and specified scores shall comply with the provisions of Table 2.2.1. 2.2.2 The quality requirements for the installation of shims and their inspection quantity, inspection methods and specified scores shall comply with the provisions of Table 2.2.2. The quality requirements for the installation of shims and their inspection quantity, inspection methods and specified scores shall comply with the provisions of Table 2.2.2. Specified score table 2.2.2 Quality requirements The hot iron should be placed as close to the anchor bolt as possible, and the spacing between adjacent shim groups is generally 500mm. Inclined shims should be used in pairs. When inclined shims are combined with flat shims, the distance should not exceed 4 and the height should be 30~70mm. The contact between the shims and the foundation should be uniform, and the contact between the shims should be close. The force should be evenly distributed and should not be tilted or inclined. The foundation space The shim group should be exposed to the bottom of the mountain by 10~30mm After leveling, the shim group should be welded intermittently Inspect the number of At least 20% of the number of fans in a room, workshop or station shall be randomly inspected, but not less than 1 unit. Inspection method: On-site inspection or tapping with a small hammer, inspection with a feeler gauge, observation inspection or inspection with a ruler. 2.2.3 Other quality requirements for fan installation and their inspection quantity, inspection methods and specified scores shall comply with the provisions of Table 2.2.3. Other quality requirements for fan installation and their inspection quantity, inspection method, and specified score table 2.2.3 Quality requirements The belt tension should be appropriate and the tightness should be consistent The rotor rotates flexibly The upper joint of the main fan cylinder, the front and rear air ducts and the diffuser connection flanges should be tightly connected The front and rear air duct diffusers should be firmly connected to the foundation Inspection quantity Inspection method Manual vibration or turning inspection Observation inspection Specified score Installation line 2.3 Allowable items The quality indicators of the fan installation allowable deviation items are subject to other inspection quantity, inspection and 2.3.1 Test method, specified score Distance from building axis Planar position of equipment Equipment elevation Horizontal degree of centrifugal fan bearing seat (per meter) Axial flow Fan Water level (per meter) Horizontal level (per meter) Two planes relative Axial displacement plate Flat pulley V-belt pulley Parallelism of two axes (per meter》 Radial displacement of two axes centering Specified value Two axes centering axis lock tilt (chain 【berry meter Outer diameter 180mm Outer diameter ≥190mm Outer diameter 30mm|| tt||External control>300~ Outer diameter#300mm Outer diameter>300~ Outer diameter170~250mm Outer diameter290430mm Outer diameter170~185mm Inspection quantity|Inspection method Tonggang tape measure inspection Use level and Connect a factory month| Check with steel ruler in the room and workshop or use level meter in the station to check the number of bearings, water umbrella strings and machines. Check with water level instrument. Check with pull line and water level. Check the shell with tools such as level ruler and meter. Check with feeler gauge. Dial indicator and Straight ruler for inspection Check with feeler gauge (per meter) Outer diameter 220-250mm Outer diameter 290-430mm Outer diameter 170~250mm Outer diameter 290~430mm Outer diameter 71~106mm||tt| |Outer diameter 130~190mm Outer diameter 224~400mm Outer diameter 475~B00mm Outer diameter 71~106mm Outer diameter 130~-260mm Outer diameter 315~475mm Outer diameter 71~106mm Outer diameter 130~190mm Outer diameter 224~400mm Outer diameter 475-600mm Outer diameter 906m Outer diameter 195~220mm Outer diameter 280~320mm Outer diameter 360~410mm Outer diameter 540~630mm Outer diameter 90~220mm Specified value||tt| |Check the number of bacteria According to a Continued Table 2.3.1 Inspection method Use a ruler and a hundred room, workshop meter, etc. to check The number of fans in the cutting station Heng Qun Wang Check with a feeler gauge Use a ruler, a hundred meter, etc. to check Check with a feeler gauge Tip: This standard content only shows part of the intercepted content of the complete standard. If you need the complete standard, please go to the top to download the complete standard document for free.