title>HG/T 20703.2-2000 The relationship between materials major and other majors - HG/T 20703.2-2000 - Chinese standardNet - bzxz.net
Home > HG > HG/T 20703.2-2000 The relationship between materials major and other majors
HG/T 20703.2-2000 The relationship between materials major and other majors

Basic Information

Standard ID: HG/T 20703.2-2000

Standard Name: The relationship between materials major and other majors

Chinese Name: 材料专业与其它各专业的关系

Standard category:Chemical industry standards (HG)

state:in force

Date of Release2000-11-22

Date of Implementation:2001-06-01

standard classification number

Standard ICS number:71.010

Standard Classification Number:Engineering Construction>>Raw Materials Industry, Communications, Broadcasting Engineering>>P72 Petrochemical, Chemical Engineering

associated standards

Publication information

other information

Introduction to standards:

HG/T 20703.2-2000 The relationship between materials and other disciplines HG/T20703.2-2000 standard download decompression password: www.bzxz.net

Some standard content:

Relationship between materials and other disciplines
HG/T 20703.2-2000
Subject content and scope of application
This standard specifies the relationship between materials and other disciplines during the engineering design stage and construction process, and is applicable to design management and engineering management of general contracting projects.
Relationship with the design manager
The design manager shall provide the following documents to this discipline: design commencement report;
Engineering design schedule;
Quality plan;
Engineering design regulations;
Approved preliminary design documents and their approval documents. This discipline shall provide the following documents to the design manager: engineering material selection regulations and pipeline material identification drawings (if any); engineering standards and regulations related to materials; technical risk memorandum.
Relationship with the project manager
In general contracting projects, when it comes to procurement, inspection and on-site construction, it is also under the leadership of the project manager and reports to the project manager. 230
4 Relationship with Chemical Process Major
Chemical Process Major needs to provide the following documents to this major: process flow chart and process description;
2 Process equipment table;
3 Data sheets of various equipment.
4.0.2 This major needs to provide the following documents to Chemical Process Major: Engineering material selection regulations and pipeline material identification diagram (if any). 5
Relationship with Process System Major
5.0.1 Process System Major needs to provide the following documents to this major: Pipeline Instrument Flow Diagram (PID) and naming table. 5.0.2 This major needs to provide the following documents to Process System Major: Engineering material selection regulations and pipeline material identification diagram (if any). 6
Relationship with Pipeline Materials Major
Pipeline Materials Major shall provide the following documents to this major: Pipeline design regulations, pipeline classification index and pipeline material classification table: Structural and manufacturing requirements for pipelines, pipe fittings and valves, etc.: Pipeline material procurement (inquiry) documents;
Quotations and relevant technical documents from pipeline material manufacturers. This major shall provide the following documents to the Pipeline Materials Major: Engineering material selection regulations and pipeline material identification diagrams (if any); Engineering standards and regulations for materials;
Propose review opinions on documents prepared by the Pipeline Materials Major and documents from pipeline material manufacturers. 231
7 Relationship with Pipeline Machinery Major
This major shall provide the Pipeline Machinery Major with engineering material selection regulations and pipeline material identification diagrams (if any); and accept consultation from the Pipeline Machinery Major on technical issues regarding materials and welding. 8 Relationship with the disciplines of containers, heat exchangers, industrial furnaces and special equipment 8.0.1bzxz.net
The above-mentioned disciplines need to provide the following documents to this discipline: design regulations of each discipline;
Procurement technical documents, including data sheets and inquiry drawings: manufacturer's quotation documents, ACF drawings and files CF drawings and files: when the manufacturing drawings are designed by our company (institute), provide the manufacturing drawings designed by our company (institute). This specialty provides the following conditions to the above-mentioned specialties: 8.0.2
Engineering material selection regulations;
Engineering standards and regulations compiled by this specialty: 2
Propose review opinions on materials and welding in the design and procurement technical documents compiled by the above-mentioned specialties 3
4Participate in the review of manufacturers' quotations, ACF, CF drawings and technical documents, and put forward review opinions, among which the welding process specifications shall be independently reviewed by this specialty and the review opinions shall be submitted to the above-mentioned specialties; 5Participate in the manufacturer coordination meeting (VCM) of the above-mentioned specialties when necessary and participate in the preparation or review of relevant meeting minutes or documents;
6When the manufacturing drawings are designed by our company (institute), put forward review opinions on the manufacturing drawings designed by it. 9
Relationship with the pump specialty
The pump specialty needs to provide the following documents to this specialty: 9.0.1
Design regulations of the pump specialty;
Procurement technical documents, including pump data sheets: 2
The manufacturer's quotation documents, ACF files and CF files. 9.0.2
This major needs to provide the following documents to the pump specialty: Engineering material selection regulations;
Engineering standards and regulations compiled by this major; 2
Review.
Propose review opinions on the materials and welding manufacturing aspects of the pump specialty design and procurement technical documents: Participate in the review of manufacturer quotations, ACF and CF technical documents and put forward review opinions; Participate in the pump specialty manufacturer coordination meeting (VCM) and participate in the preparation of relevant meeting minutes or documents when necessary. 10
Relationship with the instrument specialty
The instrument specialty needs to provide the following documents to this specialty: 10.0.1
Provide relevant instrument specialty design and procurement technical documents to this specialty when necessary. 10.0.2This major needs to provide the following documents to the instrument specialty: 1 Engineering material selection regulations and pipeline material identification diagram (if any): 2 Relevant engineering standards and regulations compiled by this major; 3 Propose material review opinions on the technical documents provided by the instrument specialty, and accept consultation on materials, welding, testing and inspection by the instrument specialty. 11
Relationship with Powder Engineering (Mechanical Transportation) and Mechanical Repair Specialties Provide engineering material selection regulations to powder engineering and mechanical repair specialties, and accept their consultation on materials, anti-corrosion, etc.
12 Relationship with Civil Engineering and Structure Specialties
This specialty accepts consultation from civil engineering and structure specialties on materials, welding, testing, etc. 233
Relationship with Procurement and Inspection Departments
Inspection is an indispensable and important part of procurement activities. This specialty participates in the following material-related work: 13.0.1
Serve as a technical consultant for the procurement department on equipment and materials; 13.0.2 For key and special material equipment, participate in the inspection work at the manufacturer, especially in material testing, welding process evaluation, welder skill assessment, and inspection test results. Provide opinions and confirmation. 14 Relationship with Construction Department
For special material equipment and pipelines manufactured on site, the material specialty participates in the review and confirmation of material testing, welding process evaluation, welder skill assessment, and inspection test results. 234