DL/T 5047-1995 Technical Specification for Construction and Acceptance of Electric Power Construction (Boiler Unit)
Some standard content:
DL_T_5047-1995 PDF
Electric Power Industry Standard of the People's Republic of China
5047 — 95
Technical Code of Erection and Acceptance ofElectric Power Construction
Section of Steam Boiler Set
1996- 01 -04 Issued
1996-05-01 Implementation
Issued by the Ministry of Electric Power Industry of the People's Republic of ChinaP
Electric Power Industry Standard of the People's Republic of China
DL/T5047—95
Technical Code of Erection and Acceptance ofElectric Power Construction
Section of Steam Boiler Set
Editor Department: Power Construction Technical and Economic Consulting Center of the Ministry of Electric Power Industry Standardization Department of China Electricity Council
Approval Department: Ministry of Electric Power Industry of the People's Republic of China Foreword
"Technical Specification for Construction and Acceptance of Power Construction (Boiler Unit)" (SDJ245-88) has played a positive role in promoting the construction of the power industry and the improvement of the construction quality of power station boilers since its release and implementation. With the rapid development of my country's socialist market economy, the development of the power industry and the improvement of power generation quality are the basic guarantees for social and economic development. In order to ensure the requirements of "safe, economic, stable and full" operation of thermal power plants and meet the needs of large units and new equipment construction, we organized relevant personnel to revise and supplement the original specifications, made major changes, and organized discussions and approvals three times. The relevant national standards, industry standards, documents, etc. adopted or quoted in this specification are all current standards and documents issued before January 1996. 36 new standards are added, 14 new standards are replaced, and 1 standard with serial number 26 in Appendix 16 of the original specification is cancelled. Due to the reference of new standards, many clauses of this specification have been modified, such as high-strength bolt connection, oil tank installation, welding process and quality, pipeline installation, pump installation, whole set startup test run, chemical cleaning, safety valve adjustment, steam flushing, etc. Due to the emergence of new equipment, new processes and new materials, this specification has also added many new clauses, including 10 new clauses of "3.5 Circulating Pump" in "3 Heating Surface", 20 new clauses of "5.5 Flue Gas Desulfurization Device" in "5 Smoke, Wind, Coal Pipeline and Ancillary Equipment", 10 new sub-clauses of "7.3.5MPS (ZGM) Medium Speed Coal Mill" in "7.3 Coal Mill", 6 new appendices, 4 revised and updated appendices, and 1 original appendix cancelled. This specification has been examined and approved by the Ministry of Electric Power Industry, and was issued on January 4, 1996 as Document No. 6 of Electric Power Technology [1996], with the serial number DL/T5047-95. It will be implemented on May 1, 1996, and the original specification SDJ245-88 will be abolished at the same time. The main editor of this specification is: Electric Power Construction Technical and Economic Consulting Center of the Ministry of Electric Power Industry Standardization Department of China Electricity Council Participating units: Electric Power Construction Research Institute of the Ministry of Electric Power Industry Editor-in-chief: Fan Jiuzhou Huan Sheng 1 General Principles 1.1 General provisions 1.2 Coordination requirements for construction projects before boiler installation 2 Boiler frame and related metal structures General provisions Boiler Foundation inspection, marking and shim installation Boiler frame assembly
Boiler frame installation and secondary grouting
Furnace door, peephole and furnace wall parts
Boiler sealing parts
Combustion device
Air preheater
Project acceptance
Heating surface
General provisions
Steam drum, header
Water-cooled wall
Superheater, reheater, economizer and temperature storage device Circulating pump
Hydrostatic test·
Project acceptance
Boiler auxiliary piping
General provisions
Boiler blowdown, sampling, heating, drainage and exhaust pipes 4.3 Water level gauge
|Safety valve
4.5 Sootblowing system
Project acceptance
5 Smoke, air, coal pipelines and ancillary equipment
General provisions·
Combination and installation of smoke, air and coal pipelines
Accessories and devices of smoke, air and coal pipelines
Coal powder separator and dust collector
Flue gas desulfurization device
Project acceptance…
Fuel system equipment and pipelines·
General provisions·
Oil unloading device and oil unloading pipeline
Oil tank and its accessories
Oil supply equipment and pump room pipeline
Plant pipeline
Fuel pipeline in boiler room
Test of fuel system and flushing
Conditions that the fuel system should meet before receiving oil
Project acceptance·
Boiler auxiliary machinery·
-General provisions
General rules for mechanical installation
Coal mill
Coal feeder
Powder feeder
Screw powder conveyor·
Air compressor
Ash equipment
Project acceptance
8Coal conveying equipment
General provisions·
Belt conveyor
Coal unloading equipment of belt conveyor
Magnetic separator
Coal crusher
Coal screen
Unloading equipment and coal yard equipment
Project acceptance
Insulation paint for boiler furnace wall, thermal equipment and pipelines 9.1
General provisions
Furnace wall and insulation materials
Refractory concrete construction
Insulation concrete construction
Frame type refractory concrete furnace wall
Pipe laying furnace wall
Brick light furnace wall
Construction of furnace wall protective layer
Insulation of thermal equipment and pipelines.·
Painting construction
Winter construction
Project acceptance
Start-up trial operation and acceptance of boiler units
-General provisions
Key points for boiler trial operation
Chemical cleaning of boilers
Pipeline flushing Cleaning and blowing
Steam tightness test and safety valve adjustment
Complete start-up test
Appendix A
Manufacturing and assembly tolerances of boiler steel structure
(Standard Appendix)
Critical temperature of commonly used steel in thermal power installationAppendix B
Reference data (Suggestive Appendix)
Appendix C Allowable deviation of the overall dimensions of boiler foundation building (Standard Appendix)
Allowable deviation of boiler reinforced concrete frame after hoistingAppendix D
(Standard Appendix)
Appendix E
Manufacturing and assembly tolerances of tubular air preheater (Standard Appendix)
Outer diameter and Appendix F Allowable deviation of wall thickness (Standard Appendix)
Allowable deviation of manufacturing dimensions of smoke, wind and coal pipelines Appendix G
(Suggestive Appendix)
Appendix H
Allowable deviation of masonry structure (Standard Appendix) Appendix J Allowable deviation of foundation of large power equipment (Standard Appendix)
Appendix K
Calculation of area of shim group (Suggestive Appendix) End clearance between elastic cylindrical pin couplings Appendix L
(Suggestive Appendix)
Appendix M
Appendix N
Appendix P
Appendix Q
Expansion clearance of load-bearing bearings (Suggestive Appendix) End runout of main bearing Value (suggestive appendix) Standard for coal unloading platform at coal unloading ditch (suggestive appendix) Track laying standard (suggestive appendix)
Current national standards, industry standards Appendix R
and regulations and rules related to this specification (suggestive appendix) Appendix S
Optional cleaning media (suggestive appendix) Appendix T
Regulations on boiler safety valves (suggestive appendix): Appendix U
Several technical terms involved in this specification (suggestive appendix) Appendix V
Explanation of terms used in this specification (suggestive appendix) 147
General provisions
1.1.1 This specification is applicable to boilers with a capacity of 65 to 2100 t/h and a main steam pressure of 3.82~25MPa, main steam temperature of 450~550℃ for domestic power station boiler units; for units with greater or less than the above capacity and parameters, this specification can be used as a reference for construction and acceptance: the construction and acceptance of foreign imported units should be carried out in accordance with the manufacturer's regulations. If the manufacturer has no clear regulations, this specification should be implemented. 1.1.2 Boiler unit installation engineering should be constructed according to the design and equipment technical documents. In addition to this specification, the relevant parts on pipelines, welding, pumps, thermal measuring instruments, etc. should be used in conjunction with the corresponding professional technical specifications of this specification:
1.1.2.1 The installation of steam pipes, water supply pipes and industrial water pipes within the boiler range shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Pipeline Section)" (DL5031-94);
1.1.2.2 The welding work in the preparation and installation of pressure pipes shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Welding Section of Thermal Power Plants)" (DL5007-92), and the non-pressure-bearing parts on important steel structures and pressure-bearing components shall be welded by welders who are suitable for this work and have passed the examination;
1.1.2.3 The installation of pumps shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Turbine Unit Section)" (DL5011-92)
1.1.2.4 The installation of thermal measuring instruments shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Thermal Instruments and Control Equipment Section)" 1.1.2.5 The anti-corrosion requirements for the heating surface of the boiler body and other related pipes shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Chemical Part of Thermal Power Plant)" (DLJ58-81); 1.1.2.6 The installation of mechanical equipment such as boiler elevators and lifting equipment shall refer to the "Elevator Installation Acceptance Code" (GB10060-93), "Mechanical Equipment Installation Engineering Construction and Acceptance Code (I), (IV), (V), (VI)" [TJ231-75 (), TJ231-78 (IV), TJ231-78 (V) and TJ231-78 (VI) and the relevant provisions of the "Elevator Installation Engineering Quality Inspection and Assessment Standard" (GBJ310-88); 1.1.2.7 If the steel structure of the steel furnace and the steel structure of the auxiliary machinery and equipment are connected by welding rivets, the relevant provisions of the "Steel Structure Engineering Construction and Acceptance Code" (GBJ20583) shall be referred to.
1.1.3 Design changes shall be carried out only after the formalities are handled in accordance with the regulations. Design change information shall be sorted out in time and well kept.
1.1.4 If the manufacturer has no clear regulations for the construction technical requirements of new products and new equipment, the construction unit, operation unit, design and manufacturing unit shall jointly study and formulate them and follow them during construction.
1.1.5 In addition to complying with the provisions of this Code, the installation and construction of boiler units shall also comply with the regulations on safety technology, boiler supervision, labor protection and fire prevention issued by the State Council and relevant departments and the regulations of the "Electric Power Industry Technical Management Regulations" (80) Electric Technology No. 267 and the "Electric Power Construction Technical Management System" (80) Fire Development No. 5.
1.1.6 Before assembly and installation, the boiler unit shall be qualified by the "1 manufacturing" and "safety inspection" organized by the construction unit (owner), and the equipment must be reviewed in accordance with the provisions of this Code. If manufacturing defects are found, they shall be submitted to the owner and the manufacturer for research, processing and visa. If the installation quality does not meet the requirements of this Code due to manufacturing defects, the owner and the manufacturer's representative shall visa.
1.1.7 For all boiler parts within the scope of boiler supervision, the manufacturer's technical documents must be obtained to prove that the materials used and the manufacturing quality meet the requirements of the "US Steam Boiler Safety Technical Supervision Regulations" (1987) No. 4 issued by the Ministry of Labor and Personnel or the "Power Industry Boiler Supervision Regulations" (SD167-85) issued by the former Ministry of Water Resources and Electric Power before construction can be promoted.
1.1.8 All installed equipment and materials should have product certificates and should be inspected and identified in accordance with the provisions of this specification. They can only be used after passing the on-site inspection. 1.1.9 Finished or semi-finished products (including smoke, wind, coal pipes, etc.) processed on site and self-produced and prepared materials (including furnace walls, insulation materials, etc.) shall be inspected in accordance with the requirements of this specification and relevant regulations, and shall be used only after they meet the requirements. 1.1.10 Before the equipment is hoisted, the temporary reinforcement facilities of the equipment shall be fully inspected, and the load-bearing welds shall be carefully inspected for appearance. 1.1.11 During the installation of the equipment, inspection and acceptance shall be carried out in a timely manner; the next process shall not be carried out without the inspection and acceptance of the previous process. Concealed projects must be inspected and accepted before they are concealed, and visas must be obtained.
1.1.12 During construction, it is necessary to frequently Keep the site clean. After the equipment is installed, before closing and before the boiler unit is started, it must be thoroughly inspected and cleaned, and no debris should be left inside.
1.1.13 The start-up and acceptance of the boiler unit must be carried out in accordance with the "Regulations on the Start-up and Acceptance of Capital Construction Projects of Thermal Power Plants" (Electric Power Construction No. 19967159) issued by the Ministry of Electric Power Industry.
1.1.14 After the installation of the boiler unit is completed, there should be complete construction technical records, which should comply with the design, equipment technical documents and the provisions of this specification. 1.1.15 After the installation of the boiler unit is completed, the following technical documents must be available: equipment defect records and visas;
1. 1 15. 11
Design change information (including necessary drawings); intermediate acceptance records and visas for concealed works (see the following chapters); 1. 1. 15. 3
Installation technical records and visas (see the following chapters); 1. 1. 15. 4
Quality inspection form;
1. 1. 15. 5J
1.1.15.6 Installation completion drawing.
1.1.16 The design, manufacture, maintenance and use of lifting and transporting machinery shall be carried out in accordance with relevant regulations and provisions. Before using newly installed, disassembled or overhauled lifting and transporting machinery, load tests shall be carried out in accordance with regulations, and protection, brakes and light signal indications shall be inspected. Only when they meet the requirements can they be put into use. Drivers or operators shall pass the examination. 1.1.17 Before construction, construction personnel shall study this specification, "Safety Work Regulations for Electric Power Construction (Part of Thermal Power Plant)" (DL5009.1-92) and relevant parts of technical operation regulations, and shall be allowed to work only after passing the safety examination. 1.1. 18 The storage of equipment before installation should be carried out according to the natural conditions, climate conditions, surrounding environment and storage time of the storage area, and refer to the "Electric Power Capital Construction Thermal Power Equipment Maintenance and Storage Regulations" (SDJ68--84) issued by the former Ministry of Water Resources and Electric Power Capital Construction and the provisions of the equipment technical documents. 3
1.1.19 During construction in winter and hot seasons, measures to prevent damage to equipment and ensure quality should be formulated according to the characteristics of the equipment and process requirements. 1.1.20 The stacking location of equipment should be in accordance with the provisions of the construction organization design, and secondary handling should be avoided as much as possible.
1.1.21 The equipment should be checked and counted together with the relevant parties after unpacking, and records should be made. After the inspection and inventory, it should be properly stored in time to prevent loss, damage and deterioration. The technical documents of the unpacked equipment should be kept as a case.
1.1.22 For boiler unit equipment that has been stored for a long time or placed in an environment with corrosive gases, the corrosion should be fully checked before installation, and treatment should be made according to the situation.
1.2 Requirements for coordination of construction works before boiler installation 1.2.1 Before boiler unit installation, the installation site should generally meet the following conditions: 1.2.1.1 Equipment foundation, underground trenches and underground facilities, as well as concrete platforms on each floor of the room should be completed. The ground should be backfilled and compacted, and the rough concrete floor should be as good as possible. The access to the plant or railway should be completed, and the requirements of the construction organization design should be met; 1.2.1.2 The equipment foundation should be inspected and accepted in accordance with the provisions of the national standard "Concrete Structure Engineering Construction and Acceptance Code" (GB50204-92); the foundation strength does not reach the design strength. It shall not bear weight when the strength grade is 70%;
1.2.1.3 When indoor installation is adopted, the roof of the room should be completed in general, and the roof waterproofing project should be completed in time; when outdoor installation is adopted, the construction plan should be considered in advance in the construction organization design so that the construction and installation projects can proceed smoothly: 1.2.1.4 The installation holes and scattered openings on each floor of the building should have reliable covers and railings;
1.2.1.5 The installation site should have reliable fire-fighting facilities, sufficient lighting and drainage facilities;bzxz.net
1.2.1.6 The remaining materials and debris from the civil construction should be cleared away in time. 1.2.2 Before the construction of the reinforced concrete boiler frame, the installation and civil engineering units should negotiate to determine the mutual coordination and special requirements between the reinforced concrete boiler frame and the boiler body construction. Before the boiler body is hoisted, the deviation of the frame construction should be fully reviewed, 42 The boiler unit installation project should be constructed according to the design and equipment technical documents. In addition to this specification, the relevant parts on pipelines, welding, pumps, thermal measuring instruments, etc. should be used in conjunction with the corresponding professional technical specifications of this specification:
1.1.2.1 The installation of steam pipes, water supply pipes and industrial water pipes within the boiler range shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Pipeline Section)" (DL5031-94);
1.1.2.2 The welding work in the preparation and installation of pressure pipes shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Welding Section of Thermal Power Plants)" (DL5007-92), and the non-pressure-bearing parts on important steel structures and pressure-bearing components shall be welded by welders who are suitable for this work and have passed the examination;
1.1.2.3 The installation of pumps shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Turbine Unit Section)" (DL5011-92)
1.1.2.4 The installation of thermal measuring instruments shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Thermal Instruments and Control Equipment Section)" 1.1.2.5 The anti-corrosion requirements for the heating surface of the boiler body and other related pipes shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Chemical Part of Thermal Power Plant)" (DLJ58-81); 1.1.2.6 The installation of mechanical equipment such as boiler elevators and lifting equipment shall refer to the "Elevator Installation Acceptance Code" (GB10060-93), "Mechanical Equipment Installation Engineering Construction and Acceptance Code (I), (IV), (V), (VI)" [TJ231-75 (), TJ231-78 (IV), TJ231-78 (V) and TJ231-78 (VI) and the relevant provisions of the "Elevator Installation Engineering Quality Inspection and Assessment Standard" (GBJ310-88); 1.1.2.7 If the steel structure of the steel furnace and the steel structure of the auxiliary machinery and equipment are connected by welding rivets, the relevant provisions of the "Steel Structure Engineering Construction and Acceptance Code" (GBJ20583) shall be referred to.
1.1.3 Design changes shall be carried out only after the formalities are handled in accordance with the regulations. Design change information shall be sorted out in time and well kept.
1.1.4 If the manufacturer has no clear regulations for the construction technical requirements of new products and new equipment, the construction unit, operation unit, design and manufacturing unit shall jointly study and formulate them and follow them during construction.
1.1.5 In addition to complying with the provisions of this Code, the installation and construction of boiler units shall also comply with the regulations on safety technology, boiler supervision, labor protection and fire prevention issued by the State Council and relevant departments and the regulations of the "Electric Power Industry Technical Management Regulations" (80) Electric Technology No. 267 and the "Electric Power Construction Technical Management System" (80) Fire Development No. 5.
1.1.6 Before assembly and installation, the boiler unit shall be qualified by the "1 manufacturing" and "safety inspection" organized by the construction unit (owner), and the equipment must be reviewed in accordance with the provisions of this Code. If manufacturing defects are found, they shall be submitted to the owner and the manufacturer for research, processing and visa. If the installation quality does not meet the requirements of this Code due to manufacturing defects, the owner and the manufacturer's representative shall visa.
1.1.7 For all boiler parts within the scope of boiler supervision, the manufacturer's technical documents must be obtained to prove that the materials used and the manufacturing quality meet the requirements of the "US Steam Boiler Safety Technical Supervision Regulations" (1987) No. 4 issued by the Ministry of Labor and Personnel or the "Power Industry Boiler Supervision Regulations" (SD167-85) issued by the former Ministry of Water Resources and Electric Power before construction can be promoted.
1.1.8 All installed equipment and materials should have product certificates and should be inspected and identified in accordance with the provisions of this specification. They can only be used after passing the on-site inspection. 1.1.9 Finished or semi-finished products (including smoke, wind, coal pipes, etc.) processed on site and self-produced and prepared materials (including furnace walls, insulation materials, etc.) shall be inspected in accordance with the requirements of this specification and relevant regulations, and shall be used only after they meet the requirements. 1.1.10 Before the equipment is hoisted, the temporary reinforcement facilities of the equipment shall be fully inspected, and the load-bearing welds shall be carefully inspected for appearance. 1.1.11 During the installation of the equipment, inspection and acceptance shall be carried out in a timely manner; the next process shall not be carried out without the inspection and acceptance of the previous process. Concealed projects must be inspected and accepted before they are concealed, and visas must be obtained.
1.1.12 During construction, it is necessary to frequently Keep the site clean. After the equipment is installed, before closing and before the boiler unit is started, it must be thoroughly inspected and cleaned, and no debris should be left inside.
1.1.13 The start-up and acceptance of the boiler unit must be carried out in accordance with the "Regulations on the Start-up and Acceptance of Capital Construction Projects of Thermal Power Plants" (Electric Power Construction No. 19967159) issued by the Ministry of Electric Power Industry.
1.1.14 After the installation of the boiler unit is completed, there should be complete construction technical records, which should comply with the design, equipment technical documents and the provisions of this specification. 1.1.15 After the installation of the boiler unit is completed, the following technical documents must be available: equipment defect records and visas;
1. 1 15. 11
Design change information (including necessary drawings); intermediate acceptance records and visas for concealed works (see the following chapters); 1. 1. 15. 3
Installation technical records and visas (see the following chapters); 1. 1. 15. 4
Quality inspection form;
1. 1. 15. 5J
1.1.15.6 Installation completion drawing.
1.1.16 The design, manufacture, maintenance and use of lifting and transporting machinery shall be carried out in accordance with relevant regulations and provisions. Before using newly installed, disassembled or overhauled lifting and transporting machinery, load tests shall be carried out in accordance with regulations, and protection, brakes and light signal indications shall be inspected. Only when they meet the requirements can they be put into use. Drivers or operators shall pass the examination. 1.1.17 Before construction, construction personnel shall study this specification, "Safety Work Regulations for Electric Power Construction (Part of Thermal Power Plant)" (DL5009.1-92) and relevant parts of technical operation regulations, and shall be allowed to work only after passing the safety examination. 1.1. 18 The storage of equipment before installation should be carried out according to the natural conditions, climate conditions, surrounding environment and storage time of the storage area, and refer to the "Electric Power Capital Construction Thermal Power Equipment Maintenance and Storage Regulations" (SDJ68--84) issued by the former Ministry of Water Resources and Electric Power Capital Construction and the provisions of the equipment technical documents. 3
1.1.19 During construction in winter and hot seasons, measures to prevent damage to equipment and ensure quality should be formulated according to the characteristics of the equipment and process requirements. 1.1.20 The stacking location of equipment should be in accordance with the provisions of the construction organization design, and secondary handling should be avoided as much as possible.
1.1.21 The equipment should be checked and counted together with the relevant parties after unpacking, and records should be made. After the inspection and inventory, it should be properly stored in time to prevent loss, damage and deterioration. The technical documents of the unpacked equipment should be kept as a case.
1.1.22 For boiler unit equipment that has been stored for a long time or placed in an environment with corrosive gases, the corrosion should be fully checked before installation and handled according to the situation.
1.2 Requirements for coordination of construction works before boiler installation 1.2.1 Before boiler unit installation, the installation site should generally meet the following conditions: 1.2.1.1 Equipment foundation, underground trenches and underground facilities, as well as concrete platforms on each floor of the room should be completed. The ground should be backfilled and compacted, and the rough concrete floor should be as good as possible. The access to the plant or railway should be completed, and the requirements of the construction organization design should be met; 1.2.1.2 The equipment foundation should be inspected and accepted in accordance with the provisions of the national standard "Concrete Structure Engineering Construction and Acceptance Code" (GB50204-92); the foundation strength does not reach the design strength. It shall not bear weight when the strength grade is 70%;
1.2.1.3 When indoor installation is adopted, the roof of the room should be completed in general, and the roof waterproofing project should be completed in time; when outdoor installation is adopted, the construction plan should be considered in advance in the construction organization design so that the construction and installation projects can proceed smoothly: 1.2.1.4 The installation holes and scattered openings on each floor of the building should have reliable covers and railings;
1.2.1.5 The installation site should have reliable fire-fighting facilities, sufficient lighting and drainage facilities;
1.2.1.6 The remaining materials and debris from the civil construction should be cleared away in time. 1.2.2 Before the construction of the reinforced concrete boiler frame, the installation and civil engineering units should negotiate to determine the mutual coordination and special requirements between the reinforced concrete boiler frame and the boiler body construction. Before the boiler body is hoisted, the deviation of the frame construction should be fully reviewed, 42 The boiler unit installation project should be constructed according to the design and equipment technical documents. In addition to this specification, the relevant parts on pipelines, welding, pumps, thermal measuring instruments, etc. should be used in conjunction with the corresponding professional technical specifications of this specification:
1.1.2.1 The installation of steam pipes, water supply pipes and industrial water pipes within the boiler range shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Pipeline Section)" (DL5031-94);
1.1.2.2 The welding work in the preparation and installation of pressure pipes shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Welding Section of Thermal Power Plants)" (DL5007-92), and the non-pressure-bearing parts on important steel structures and pressure-bearing components shall be welded by welders who are suitable for this work and have passed the examination;
1.1.2.3 The installation of pumps shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Turbine Unit Section)" (DL5011-92)
1.1.2.4 The installation of thermal measuring instruments shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Thermal Instruments and Control Equipment Section)" 1.1.2.5 The anti-corrosion requirements for the heating surface of the boiler body and other related pipes shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Chemical Part of Thermal Power Plant)" (DLJ58-81); 1.1.2.6 The installation of mechanical equipment such as boiler elevators and lifting equipment shall refer to the "Elevator Installation Acceptance Code" (GB10060-93), "Mechanical Equipment Installation Engineering Construction and Acceptance Code (I), (IV), (V), (VI)" [TJ231-75 (), TJ231-78 (IV), TJ231-78 (V) and TJ231-78 (VI) and the relevant provisions of the "Elevator Installation Engineering Quality Inspection and Assessment Standard" (GBJ310-88); 1.1.2.7 If the steel structure of the steel furnace and the steel structure of the auxiliary machinery and equipment are connected by welding rivets, the relevant provisions of the "Steel Structure Engineering Construction and Acceptance Code" (GBJ20583) shall be referred to.
1.1.3 Design changes shall be carried out only after the formalities are handled in accordance with the regulations. Design change information shall be sorted out in time and well kept.
1.1.4 If the manufacturer has no clear regulations for the construction technical requirements of new products and new equipment, the construction unit, operation unit, design and manufacturing unit shall jointly study and formulate them and follow them during construction.
1.1.5 In addition to complying with the provisions of this Code, the installation and construction of boiler units shall also comply with the regulations on safety technology, boiler supervision, labor protection and fire prevention issued by the State Council and relevant departments and the regulations of the "Electric Power Industry Technical Management Regulations" (80) Electric Technology No. 267 and the "Electric Power Construction Technical Management System" (80) Fire Development No. 5.
1.1.6 Before assembly and installation, the boiler unit shall be qualified by the "1 manufacturing" and "safety inspection" organized by the construction unit (owner), and the equipment must be reviewed in accordance with the provisions of this Code. If manufacturing defects are found, they shall be submitted to the owner and the manufacturer for research, processing and visa. If the installation quality does not meet the requirements of this Code due to manufacturing defects, the owner and the manufacturer's representative shall visa.
1.1.7 For all boiler parts within the scope of boiler supervision, the manufacturer's technical documents must be obtained to prove that the materials used and the manufacturing quality meet the requirements of the "US Steam Boiler Safety Technical Supervision Regulations" (1987) No. 4 issued by the Ministry of Labor and Personnel or the "Power Industry Boiler Supervision Regulations" (SD167-85) issued by the former Ministry of Water Resources and Electric Power before construction can be promoted.
1.1.8 All installed equipment and materials should have product certificates and should be inspected and identified in accordance with the provisions of this specification. They can only be used after passing the on-site inspection. 1.1.9 Finished or semi-finished products (including smoke, wind, coal pipes, etc.) processed on site and self-produced and prepared materials (including furnace walls, insulation materials, etc.) shall be inspected in accordance with the requirements of this specification and relevant regulations, and shall be used only after they meet the requirements. 1.1.10 Before the equipment is hoisted, the temporary reinforcement facilities of the equipment shall be fully inspected, and the load-bearing welds shall be carefully inspected for appearance. 1.1.11 During the installation of the equipment, inspection and acceptance shall be carried out in a timely manner; the next process shall not be carried out without the inspection and acceptance of the previous process. Concealed projects must be inspected and accepted before they are concealed, and visas must be obtained.
1.1.12 During construction, it is necessary to frequently Keep the site clean. After the equipment is installed, before closing and before the boiler unit is started, it must be thoroughly inspected and cleaned, and no debris should be left inside.
1.1.13 The start-up and acceptance of the boiler unit must be carried out in accordance with the "Regulations on the Start-up and Acceptance of Capital Construction Projects of Thermal Power Plants" (Electric Power Construction No. 19967159) issued by the Ministry of Electric Power Industry.
1.1.14 After the installation of the boiler unit is completed, there should be complete construction technical records, which should comply with the design, equipment technical documents and the provisions of this specification. 1.1.15 After the installation of the boiler unit is completed, the following technical documents must be available: equipment defect records and visas;
1. 1 15. 11
Design change information (including necessary drawings); intermediate acceptance records and visas for concealed works (see the following chapters); 1. 1. 15. 3
Installation technical records and visas (see the following chapters); 1. 1. 15. 4
Quality inspection form;
1. 1. 15. 5J
1.1.15.6 Installation completion drawing.
1.1.16 The design, manufacture, maintenance and use of lifting and transporting machinery shall be carried out in accordance with relevant regulations and provisions. Before using newly installed, disassembled or overhauled lifting and transporting machinery, load tests shall be carried out in accordance with regulations, and protection, brakes and light signal indications shall be inspected. Only when they meet the requirements can they be put into use. Drivers or operators shall pass the examination. 1.1.17 Before construction, construction personnel shall study this specification, "Safety Work Regulations for Electric Power Construction (Part of Thermal Power Plant)" (DL5009.1-92) and relevant parts of technical operation regulations, and shall be allowed to work only after passing the safety examination. 1.1. 18 The storage of equipment before installation should be carried out according to the natural conditions, climate conditions, surrounding environment and storage time of the storage area, and refer to the "Electric Power Capital Construction Thermal Power Equipment Maintenance and Storage Regulations" (SDJ68--84) issued by the former Ministry of Water Resources and Electric Power Capital Construction and the provisions of the equipment technical documents. 3
1.1.19 During construction in winter and hot seasons, measures to prevent damage to equipment and ensure quality should be formulated according to the characteristics of the equipment and process requirements. 1.1.20 The stacking location of equipment should be in accordance with the provisions of the construction organization design, and secondary handling should be avoided as much as possible.
1.1.21 The equipment should be checked and counted together with the relevant parties after unpacking, and records should be made. After the inspection and inventory, it should be properly stored in time to prevent loss, damage and deterioration. The technical documents of the unpacked equipment should be kept as a case.
1.1.22 For boiler unit equipment that has been stored for a long time or placed in an environment with corrosive gases, the corrosion should be fully checked before installation, and treatment should be made according to the situation.
1.2 Requirements for coordination of construction works before boiler installation 1.2.1 Before boiler unit installation, the installation site should generally meet the following conditions: 1.2.1.1 Equipment foundation, underground trenches and underground facilities, as well as concrete platforms on each floor of the room should be completed. The ground should be backfilled and compacted, and the rough concrete floor should be as good as possible. The access to the plant or railway should be completed, and the requirements of the construction organization design should be met; 1.2.1.2 The equipment foundation should be inspected and accepted in accordance with the provisions of the national standard "Concrete Structure Engineering Construction and Acceptance Code" (GB50204-92); the foundation strength does not reach the design strength. It shall not bear weight when the strength grade is 70%;
1.2.1.3 When indoor installation is adopted, the roof of the room should be completed in general, and the roof waterproofing project should be completed in time; when outdoor installation is adopted, the construction plan should be considered in advance in the construction organization design so that the construction and installation projects can proceed smoothly: 1.2.1.4 The installation holes and scattered openings on each floor of the building should have reliable covers and railings;
1.2.1.5 The installation site should have reliable fire-fighting facilities, sufficient lighting and drainage facilities;
1.2.1.6 The remaining materials and debris from the civil construction should be cleared away in time. 1.2.2 Before the construction of the reinforced concrete boiler frame, the installation and civil engineering units should negotiate to determine the mutual coordination and special requirements between the reinforced concrete boiler frame and the boiler body construction. Before the boiler body is hoisted, the deviation of the frame construction should be fully reviewed, 42 The welding work in the preparation and installation of pressure pipelines shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Welding of Thermal Power Plants)" (DL5007-92). The non-pressure-bearing parts on important steel structures and pressure-bearing parts shall be welded by welders who are suitable for this work and have passed the examination;
1.1.2.3 The installation of pumps shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Steam Turbine Units)" (DL5011-92)
1.1.2.4 The installation of thermal measuring instruments shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Thermal Instruments and Control Devices)" (SDJ27990); 1.1.2.5 The anti-corrosion requirements for the heating surface of the boiler body and other related piping systems shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Thermal Power Plants)" 1.1.2.6 The installation of mechanical equipment such as boiler elevators and lifting equipment shall refer to the relevant provisions of the "Elevator Installation Acceptance Code" (GB10060-93), "Mechanical Equipment Installation Engineering Construction and Acceptance Code (I), (IV), (V), (VI)" [TJ231-75 (), TJ231-78 (IV), TJ231-78 (V) and TJ231-78 (VI) and "Elevator Installation Engineering Quality Inspection and Evaluation Standard" (GBJ310-88); 1.1.2.7 If the steel structure of the steel furnace and the steel structure of the auxiliary machinery and equipment are connected by welding rivets, they shall refer to the relevant provisions of the "Steel Structure Engineering Construction and Acceptance Code" (GBJ20583).
1.1.3 Construction is allowed only after the design change procedures are handled in accordance with the regulations. Design change information should be sorted out in time and kept well.
1.1.4 If the manufacturer has no clear regulations on the construction technical requirements for new products and new equipment, the construction unit, operation unit, design and manufacturing unit shall jointly study and formulate them and implement them during construction.
1.1.5 In addition to the provisions of this code, the installation and construction of boiler units shall also comply with the safety technology, boiler supervision, labor protection and fire prevention regulations issued by the State Council and relevant departments and the regulations of the "Electric Power Industry Technical Management Regulations" (80) Electric Technology No. 26 and "Electric Power Construction Technical Management System" (80) Fire No. 5.
1.1.6 Before assembly and installation, the boiler unit shall be qualified by the construction unit (owner) for "1 manufacturing" and "1 safety inspection", and the equipment must be reviewed in accordance with the provisions of this code. If manufacturing defects are found, they shall be submitted to the owner and the manufacturer for research, processing and certification. If the installation quality does not meet the requirements of this code due to manufacturing defects, the owner and the manufacturer's representative shall sign.
1.1.7 For all boiler parts within the scope of boiler supervision, the manufacturer's technical documents must be obtained to prove that the materials used and the manufacturing quality meet the requirements of the "US Steam Boiler Safety Technical Supervision Regulations" (1987) No. 4 issued by the Ministry of Labor and Personnel or the "Power Industry Boiler Supervision Regulations" (SD167-85) issued by the former Ministry of Water Resources and Electric Power before construction can be promoted.
1.1.8 All installed equipment and materials should have product certificates and should be inspected and identified in accordance with the provisions of this specification. They can only be used after passing the on-site inspection. 1.1.9 Finished or semi-finished products (including smoke, wind, coal pipes, etc.) processed on site and self-produced and prepared materials (including furnace walls, insulation materials, etc.) shall be inspected in accordance with the requirements of this specification and relevant regulations, and shall be used only after they meet the requirements. 1.1.10 Before the equipment is hoisted, the temporary reinforcement facilities of the equipment shall be fully inspected, and the load-bearing welds shall be carefully inspected for appearance. 1.1.11 During the installation of the equipment, inspection and acceptance shall be carried out in a timely manner; the next process shall not be carried out without the inspection and acceptance of the previous process. Concealed projects must be inspected and accepted before they are concealed, and visas must be obtained.
1.1.12 During construction, it is necessary to frequently Keep the site clean. After the equipment is installed, before closing and before the boiler unit is started, it must be thoroughly inspected and cleaned, and no debris should be left inside.
1.1.13 The start-up and acceptance of the boiler unit must be carried out in accordance with the "Regulations on the Start-up and Acceptance of Capital Construction Projects of Thermal Power Plants" (Electric Power Construction No. 19967159) issued by the Ministry of Electric Power Industry.
1.1.14 After the installation of the boiler unit is completed, there should be complete construction technical records, which should comply with the design, equipment technical documents and the provisions of this specification. 1.1.15 After the installation of the boiler unit is completed, the following technical documents must be available: equipment defect records and visas;
1. 1 15. 11
Design change information (including necessary drawings); intermediate acceptance records and visas for concealed works (see the following chapters); 1. 1. 15. 3
Installation technical records and visas (see the following chapters); 1. 1. 15. 4
Quality inspection form;
1. 1. 15. 5J
1.1.15.6 Installation completion drawing.
1.1.16 The design, manufacture, maintenance and use of lifting and transporting machinery shall be carried out in accordance with relevant regulations and provisions. Before using newly installed, disassembled or overhauled lifting and transporting machinery, load tests shall be carried out in accordance with regulations, and protection, brakes and light signal indications shall be inspected. Only when they meet the requirements can they be put into use. Drivers or operators shall pass the examination. 1.1.17 Before construction, construction personnel shall study this specification, "Safety Work Regulations for Electric Power Construction (Part of Thermal Power Plant)" (DL5009.1-92) and relevant parts of technical operation regulations, and shall be allowed to work only after passing the safety examination. 1.1. 18 The storage of equipment before installation should be carried out according to the natural conditions, climate conditions, surrounding environment and storage time of the storage area, and refer to the "Electric Power Capital Construction Thermal Power Equipment Maintenance and Storage Regulations" (SDJ68--84) issued by the former Ministry of Water Resources and Electric Power Capital Construction and the provisions of the equipment technical documents. 3
1.1.19 During construction in winter and hot seasons, measures to prevent damage to equipment and ensure quality should be formulated according to the characteristics of the equipment and process requirements. 1.1.20 The stacking location of equipment should be in accordance with the provisions of the construction organization design, and secondary handling should be avoided as much as possible.
1.1.21 The equipment should be checked and counted together with the relevant parties after unpacking, and records should be made. After the inspection and inventory, it should be properly stored in time to prevent loss, damage and deterioration. The technical documents of the unpacked equipment should be kept as a case.
1.1.22 For boiler unit equipment that has been stored for a long time or placed in an environment with corrosive gases, the corrosion should be fully checked before installation and handled according to the situation.
1.2 Requirements for coordination of construction works before boiler installation 1.2.1 Before boiler unit installation, the installation site should generally meet the following conditions: 1.2.1.1 Equipment foundation, underground trenches and underground facilities, as well as concrete platforms on each floor of the room should be completed. The ground should be backfilled and compacted, and the rough concrete floor should be as good as possible. The access to the plant or railway should be completed, and the requirements of the construction organization design should be met; 1.2.1.2 The equipment foundation should be inspected and accepted in accordance with the provisions of the national standard "Concrete Structure Engineering Construction and Acceptance Code" (GB50204-92); the foundation strength does not reach the design strength. It shall not bear weight when the strength grade is 70%;
1.2.1.3 When indoor installation is adopted, the roof of the room should be completed in general, and the roof waterproofing project should be completed in time; when outdoor installation is adopted, the construction plan should be considered in advance in the construction organization design so that the construction and installation projects can proceed smoothly: 1.2.1.4 The installation holes and scattered openings on each floor of the building should have reliable covers and railings;
1.2.1.5 The installation site should have reliable fire-fighting facilities, sufficient lighting and drainage facilities;
1.2.1.6 The remaining materials and debris from the civil construction should be cleared away in time. 1.2.2 Before the construction of the reinforced concrete boiler frame, the installation and civil engineering units should negotiate to determine the mutual coordination and special requirements between the reinforced concrete boiler frame and the boiler body construction. Before the boiler body is hoisted, the deviation of the frame construction should be fully reviewed, 42 The welding work in the preparation and installation of pressure pipelines shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Welding of Thermal Power Plants)" (DL5007-92). The non-pressure-bearing parts on important steel structures and pressure-bearing parts shall be welded by welders who are suitable for this work and have passed the examination;
1.1.2.3 The installation of pumps shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Steam Turbine Units)" (DL5011-92)
1.1.2.4 The installation of thermal measuring instruments shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Thermal Instruments and Control Devices)" (SDJ27990); 1.1.2.5 The anti-corrosion requirements for the heating surface of the boiler body and other related piping systems shall comply with the "Technical Specifications for Construction and Acceptance of Electric Power Construction (Thermal Power Plants)" 1.1.2.6 The installation of mechanical equipment such as boiler elevators and lifting equipment shall refer to the relevant provisions of the "Elevator Installation Acceptance Code" (GB10060-93), "Mechanical Equipment Installation Engineering Construction and Acceptance Code (I), (IV), (V), (VI)" [TJ231-75 (), TJ231-78 (IV), TJ231-78 (V) and TJ231-78 (VI) and "Elevator Installation Engineering Quality Inspection and Evaluation Standard" (GBJ310-88); 1.1.2.7 If the steel structure of the steel furnace and the steel structure of the auxiliary machinery and equipment are connected by welding rivets, they shall refer to the relevant provisions of the "Steel Structure Engineering Construction and Acceptance Code" (GBJ20583).
1.1.3 Construction is allowed only after the design change procedures are handled in accordance with the regulations. Design change information should be sorted out in time and kept well.
1.1.4 If the manufacturer has no clear regulations on the construction technical requirements for new products and new equipment, the construction unit, operation unit, design and manufacturing unit shall jointly study and formulate them and implement them during construction.
1.1.5 In addition to the provisions of this code, the installation and construction of boiler units shall also comply with the safety technology, boiler supervision, labor protection and fire prevention regulations issued by the State Council and relevant departments and the regulations of the "Electric Power Industry Technical Management Regulations" (80) Electric Technology No. 26 and "Electric Power Construction Technical Management System" (80) Fire No. 5.
1.1.6 Before assembly and installation, the boiler unit shall be qualified by the construction unit (owner) for "1 manufacturing" and "1 safety inspection", and the equipment must be reviewed in accordance with the provisions of this code. If manufacturing defects are found, they shall be submitted to the owner and the manufacturer for research, processing and certification. If the installation quality does not meet the requirements of this code due to manufacturing defects, the owner and the manufacturer's representative shall sign.
1.1.7 For all boiler parts within the scope of boiler supervision, the manufacturer's technical documents must be obtained to prove that the materials used and the manufacturing quality meet the requirements of the "US Steam Boiler Safety Technical Supervision Regulations" (1987) No. 4 issued by the Ministry of Labor and Personnel or the "Power Industry Boiler Supervision Regulations" (SD167-85) issued by the former Ministry of Water Resources and Electric Power before construction can be promoted.
1.1.8 All installed equipment and materials should have product certificates and should be inspected and identified in accordance with the provisions of this specification. They can only be used after passing the on-site inspection. 1.1.9 Finished or semi-finished products (including smoke, wind, coal pipes, etc.) processed on site and self-produced and prepared materials (including furnace walls, insulation materials, etc.) shall be inspected in accordance with the requirements of this specification and relevant regulations, and shall be used only after they meet the requirements. 1.1.10 Before the equipment is hoisted, the temporary reinforcement facilities of the equipment shall be fully inspected, and the load-bearing welds shall be carefully inspected for appearance. 1.1.11 During the installation of the equipment, inspection and acceptance shall be carried out in a timely manner; the next process shall not be carried out without the inspection and acceptance of the previous process. Concealed projects must be inspected and accepted before they are concealed, and visas must be obtained.
1.1.12 During construction, it is necessary to frequently Keep the site clean. After the equipment is installed, before closing and before the boiler unit is started, it must be thoroughly inspected and cleaned, and no debris should be left inside.
1.1.13 The start-up and acceptance of the boiler unit must be carried out in accordance with the "Regulations on the Start-up and Acceptance of Capital Construction Projects of Thermal Power Plants" (Electric Power Construction No. 19967159) issued by the Ministry of Electric Power Industry.
1.1.14 After the installation of the boiler unit is completed, there should be complete construction technical records, which should comply with the design, equipment technical documents and the provisions of this specification. 1.1.15 After the installation of the boiler unit is completed, the following technical documents must be available: equipment defect records and visas;
1. 1 15. 11
Design change information (including necessary drawings); intermediate acceptance records and visas for concealed works (see the following chapters); 1. 1. 15. 3
Installation technical records and visas (see the following chapters); 1. 1. 15. 4
Quality inspection form;
1. 1. 15. 5J
1.1.15.6 Installation completion drawing.
1.1.16 The design, manufacture, maintenance and use of lifting and transporting machinery shall be carried out in accordance with relevant regulations and provisions. Before using newly installed, disassembled or overhauled lifting and transporting machinery, load tests shall be carried out in accordance with regulations, and protection, brakes and light signal indications shall be inspected. Only when they meet the requirements can they be put into use. Drivers or operators shall pass the examination. 1.1.17 Before construction, construction personnel shall study this specification, "Safety Work Regulations for Electric Power Construction (Part of Thermal Power Plant)" (DL5009.1-92) and relevant parts of technical operation regulations, and shall be allowed to work only after passing the safety examination. 1.1. 18 The storage of equipment before installation should be carried out according to the natural conditions, climate conditions, surrounding environment and storage time of the storage area, and refer to the "Electric Power Capital Construction Thermal Power Equipment Maintenance and Storage Regulations" (SDJ68--84) issued by the former Ministry of Water Resources and Electric Power Capital Construction and the provisions of the equipment technical documents. 3
1.1.19 During construction in winter and hot seasons, measures to prevent damage to equipment and ensure quality should be formulated according to the characteristics of the equipment and process requirements. 1.1.20 The stacking location of equipment should be in accordance with the provisions of the construction organization design, and secondary handling should be avoided as much as possible.
1.1.21 The equipment should be checked and counted together with the relevant parties after unpacking, and records should be made. After the inspection and inventory, it should be properly stored in time to prevent loss, damage and deterioration. The technical documents of the unpacked equipment should be kept as a case.
1.1.22 For boiler unit equipment that has been stored for a long time or placed in an environment with corrosive gases, the corrosion should be fully checked before installation and handled according to the situation.
1.2 Requirements for coordination of construction works before boiler installation 1.2.1 Before boiler unit installation, the installation site should generally meet the following conditions: 1.2.1.1 Equipment foundation, underground trenches and underground facilities, as well as concrete platforms on each floor of the room should be completed. The ground should be backfilled and compacted, and the rough concrete floor should be as good as possible. The access to the plant or railway should be completed, and the requirements of the construction organization design should be met; 1.2.1.2 The equipment foundation should be inspected and accepted in accordance with the provisions of the national standard "Concrete Structure Engineering Construction and Acceptance Code" (GB50204-92); the foundation strength does not reach the design strength. It shall not bear weight when the strength grade is 70%;
1.2.1.3 When indoor installation is adopted, the roof of the room should be completed in general, and the roof waterproofing project should be completed in time; when outdoor installation is adopted, the construction plan should be considered in advance in the construction organization design so that the construction and installation projects can proceed smoothly: 1.2.1.4 The installation holes and scattered openings on each floor of the building should have reliable covers and railings;
1.2.1.5 The installation site should have reliable fire-fighting facilities, sufficient lighting and drainage facilities;
1.2.1.6 The remaining materials and debris from the civil construction should be cleared away in time. 1.2.2 Before the construction of the reinforced concrete boiler frame, the installation and civil engineering units should negotiate to determine the mutual coordination and special requirements between the reinforced concrete boiler frame and the boiler body construction. Before the boiler body is hoisted, the deviation of the frame construction should be fully reviewed, 46 The installation of mechanical equipment such as boiler elevators and lifting equipment should refer to the relevant provisions of the "Elevator Installation Acceptance Code" (GB10060-93), "Mechanical Equipment Installation Engineering Construction and Acceptance Code (I), (IV), (V), (VI)" [TJ231-75 (), TJ231-78 (IV), TJ231-78 (V) and TJ231-78 (VI) and "Elevator Installation Engineering Quality Inspection and Evaluation Standard" (GBJ310-88); 1.1.2.7 If the steel structure of the steel furnace and the steel structure of the auxiliary machinery and equipment are connected by welding rivets, they should refer to the relevant provisions of the "Steel Structure Engineering Construction and Acceptance Code" (GBJ20583).
1.1.3 Design changes shall be handled in accordance with the prescribed procedures before construction is allowed. Design change information should be sorted out in a timely manner and kept well.
1.1.4 If the manufacturer has no clear regulations on the construction technical requirements for new products and new equipment, the construction unit, operation unit, design and manufacturing unit shall jointly study and formulate them and implement them during construction.
1.1.5 In addition to the provisions of this code, the installation and construction of boiler units shall also comply with the safety technology, boiler supervision, labor protection and fire prevention regulations issued by the State Council and relevant departments and the regulations of the "Electric Power Industry Technical Management Regulations" (80) Electric Technology No. 26 and "Electric Power Construction Technical Management System" (80) Fire No. 5.
1.1.6 Before assembly and installation, the boiler unit shall be qualified by the construction unit (owner) for "1 manufacturing" and "1 safety inspec